small scale incinerator

Incinerators Biological waste disposal system (incinerator)

Incinerator must meet the following specifications:

–       Combustion capacity (kW) = 581 +/-10%

–       Combustion capacity (kcal/h) = 500,000 +/-10%

–       Max. l/h (at approx.. 50% water content) = 100 +/-10%

Further specifications will be provided with the inquiry.

The incinerator shall be fully self contained.

The incinerator plant shall incorporate a control panel for its operation. On the control panel we shall have a visual display of the chamber temperatures. This visual display must control and monitor the incinerator and his performance.

Capacity of destruction in weight shall be 60 Kg/h.

It should be able to operate not less than 10 hours/day

This incinerator must be able to destruct all combustible wastes produced by hospitals, private clinics, laboratories, institutes, etc…

Design Specification : Types A, B, C, D, and E of medical waste

“PYROLYTIC” combustion, by controlling the gasification of waste.

The incinerator must avoid the release of black smoke and fine dust, during the loadings.

It shall be able to reduce the volume of wastes by 98%.

It shall be able to hold emission in the second burn with gas residence of not less than 2 seconds.

The incineration should be completely free from visible smoke as well as offensive odours.

1.0The primary ignition burner shall providing ignition of the waste to 850 °C and must switch off to conserve fuel.

The primary combustion chamber shall be constructed from heavy steel plate and the unit is internally lined with a complete layer of hote face refractory and high efficiency insulation.

The Internal diameter of the Chimney at least: ? 400 and its height: 8 m

The Volume of the combustion chamber at least: 1.200 L

The Dimension of the door for loading in cm at least: 70×70.

Burner operation should be Automatic On/Off
Fuel?: diesel

Manufacturer to provide  necessary information for the best of  the installation

The control panel shall have all appropriate audible and visual alarms to ensure safe operation.

This incinerator with “PYROLYTIC” combustion must have:
1.A combustion chamber of waste:
oPerfectly tight door for the manual loading of waste. The loading should be Manual, Batch Load
oA burner of lighting which the use is limited to the ignition of waste.
oFrontage of loading with door seals gone up on hinges, wheel of screw plug, flexible joint, and stuffing insulating out of refractory.
oThe insulation of the combustion chamber should be composed of refractory bricks, having a high content of aluminium and insulates bricks in order to assure a minimum temperature on the outside sheet metal.
o Composition of the refractory;

?Refractory concrete :
. Thickness    : ≥100 mm
. Nature: 42% of Al203
?Insulate in fibrous panels :
Thickness: ≥75 mm
Nature: Calcium silicate.
?Burner of lighting of waste, with fuel, standard mono-bloc casting guiding  plunging flame, lighting and safety of electronic ignition, permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.
Plate of combustion in Carborundum, avoiding the fixing of glass and slags

A chamber of post combustion of gases
oA burner of combustion of gases,
oA device of injection of air allowing a total recombustion of gases,
oA device of air inlet of cooling of waste gases,
oA sheath of evacuation of the gases burnt.
oCarcass in strong sheet steel with support of connection.
oComposition of the refractory;
?Refractory concrete :
?Thickness    : ≥150 mm
?Nature: 65% of Al203
?Insulate in fibrous panel :
?Thickness: ≥85 mm
? Nature: Calcium
oBurner with fuel, mono-bloc casting guiding type with horizontal flame, lighting and safety of electronic ignition, permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.
oA secondary injection of air to ensure perfect oxygen content.

A control box ensuring the complete cycle of combustion.

Fan:
oElectro-ventilator distributing the secondary air, the regulation of the air flow being carried out by valves and following the control of the automatic cycle.
Controls and regulations:
Control box watertight to dust, including:

A switch circuit breaker for each engine (ventilators and burners).
A timer with adjustable temporization for the regulation of each burner.
A regulator with digital watching for the temperature of combustion.
A regulator with digital watching for the temperature of post combustion.
Electric box

The secondary combustion chamber must destroy the contaminant product and must resist to high temperature(1100 °C)

Process Filtering system: Scruber to be mentionned as optional

medical incinerator design

It is expected that the Bidder will cooperate closely with PATH and target Hospitals for the new waste handling

building/area and will make available all needed technical information, drawings, etc.,

 

The following waste streams shall be treated in the new HCW treatment center(s):

 

Infectious waste

 

Sharps waste

 

Pathological waste

 

Pharmaceutical waste including cytotoxic or genotoxic waste

 

Small amounts of chemical waste

TECHNICAL SPECIFICATION FOR PROCUREMENT OF “MEDICAL WASTE TREATMENT PLANT”

Lot-A

Specification

1.Hydroclave for Medical waste Treatment Plant: Quantity: 02 Nos.

General Requirements

The processor must be approved to sterilize  & treat the following types of medical waste:

-Liquids: Blood, body fluids etc.

-Blood bags & tubing, gloves, Gowns, drapes, etc.

-Contaminated packaging: bandage etc.

-Sharps & Sharp containers

-Disposable instruments

-Glass products

-Human and animal tissue (surgical and pathologic) –Based upon MWM regulations

-Cultures, stocks and glassware

The processor must comply with a documented efficacy level of 6log10 reduction in spore survival (99,9999%) of the

Bacillus Stearothermophilus

The processor should reduce the volume of the waste by 60% to 80% through complete dehydration and sterilization of

the waste

The  processor must have ZERO harmful emission level and meet or exceed all standards required by the EU.

The whole waste treatment system should be offered as a complete unit consisting of following equipment and

ancillaries-

(A)The sterilization processing unit

(B)Steam Boiler

(C)Tub washer

(D)Heavy duty external shredder-

(E)Conveyer belt-based on Manufacturer’s Recommendations

(F)Bin Lift/Tipper

(G)Spore tester

(A)Features and Specifications of the Sterilization Processor unit:

Technical specification of the processor:

Steam autoclave in combination with a heavy duty Fragmenting System inside the vessel/chamber

The vessel must be of Double Chamber

Capacity (kg/load) : minimum 200 kg/batch/cycle

Volume of 140-190 liters of bulk per cycle

Average Cycle time : 60 minutes

Operating temperature: 121◦C to 135◦C

Operating pressure : 1.1 Bar to 2.4 Bar

Контейнерный мобильный мусоросжигатель с двойной камерой сжигания

Установка для сжигания отходов, установленная в контейнере ISO 20 ” или 40 ‘перед отправкой с завода. Нормальная скорость сжигания отходов от 10 кг до 150 кг в час.

Двойная камера сгорания

Схема установки для сжигания с первичной камерой сгорания, дополнительной камерой сгорания (запись в блоге), а также с дополнительным сухим скруббером. Этот стиль уменьшает количество черного дыма, полностью рассеивает и является экологически чистым.

Бесплатная установка

Инсинератор, размещенный в настоящее время в контейнере, вместе с топливной системой, электрической системой, а также контрольной ситуацией уже отремонтирован. Разберитесь с дымовым валом и подключите электрооборудование, ожидая работы.

Мобильный мусоросжигательный завод

Горелка для отходов размещена в контейнере ISO 20 или 40 дюймов. Его можно перемещать вместе с автомобилем в любое место или в случае необходимости.

Контейнерный мусоросжигательный завод

Цена: до 150 кг в час.

Контейнерный мусоросжигательный завод: мы отправляем мусоросжигательный завод, а также контейнер клиентам, нет необходимости строить мусоросжигательный комплекс.

Двойная камера сгорания

Камера сгорания: до 1500 литров

Сжигание ключей для подачи отходов, а также сжигание и дополнительное сжигание только для плавления дыма.

Мусоросжигательный завод, перемещаемый на грузовике

Количество вес: от 4 тонн до 9 тонн

Мобильная функция в любом месте или решение для клиента на веб-сайте их района.

Hospital Medical Waste Incinerators

Model Capacity/Burnning Rate For Hospital SickBed No. Fuel Type Qty. Ready for Shipping New Production  Shipping Volume Shipping Weight Delivery Location
TS30 average 30kgs per hour Average 150 SickBed Diesel Oil 1 set 5 days 20sets/2 weeks 5 m3 3000 kgs Shanghai Port
TS50 average 50kgs per hour Average 250 SickBed Diesel Oil 1 set 7 days 20sets/2 weeks 7m3 4500 kgs Shanghai Port
TS100 average 100kgs per hour Average 500 SickBed Diesel Oil 1 set 7 days 15sets/2 weeks 10m3 6000 kgs Shanghai Port
TS150 average 150kgs per hour Average 750 SickBed Diesel Oil 5 sets 7 days 15sets/2 weeks 13m3 7500 kgs Shanghai Port
YD10 average 10kgs per hour Average 50 SickBed Diesel Oil 2sets 7 days 20sets/2 weeks 3m3 1200 kgs Shanghai Port
YD20C average 20kgs per hour Average 100 SickBed Diesel Oil 2sets 7 days 20sets/2 weeks 6m3 2000 kgs Shanghai Port
YD50C average 50kgs per hour Average 250 SickBed Diesel Oil 2sets 7 days 20sets/2 weeks 7m3 2300 kgs Shanghai Port
YD30 average 30kgs per hour Average 150 SickBed Diesel Oil 1 set 5 days 20sets/2 weeks 5m3 2300 kgs Shanghai Port
YD30 Small average 30kgs per hour Average 150 SickBed Diesel Oil 2sets 5 days 20sets/2 weeks 3m3 1500 kgs Shanghai Port
YD50 average 50kgs per hour Average 250 SickBed Diesel Oil 2 sets 5 days 20sets/2 weeks 8m3 4500 kgs Shanghai Port
YD100 average 100kgs per hour Average 500 SickBed Diesel Oil 1 set 10 days 15sets/2 weeks 13m3 6000 kgs Shanghai Port
YD150 average 150kgs per hour Average 750 SickBed Diesel Oil 1 set 10 days 15sets/2 weeks 17m3 7500 kgs Shanghai Port
YD300 average 300kgs per hour Average 1500 SickBed Diesel Oil 10sets/2 weeks 20m3 9000 kgs Shanghai Port
YD500 average 500kgs per hour Average 2500 SickBed Diesel Oil 5sets/2 weeks 27m3 13000 kgs Shanghai Port
CA 50 Mobile Containerized average 50kgs per hour Average 250 SickBed Diesel Oil 2 sets 15 days 10sets/2 weeks 28m3 7000 kgs Shanghai Port
HICLOVER – Medical Environmental 


 

Waste Incinerators
Medical Waste Incinerator
Pet Animal Cremation
Solid Waste Incinerator

Tel:  +86-25-8461 0201   
Mobile: +86-13813931455(whatsapp/wechat)
Website: www.hiclover.com  
Email: [email protected]
Email: [email protected]  
Nanjing Clover Medical Technology Co.,Ltd.

 

2020-04-08

fabricantes de incineradores de hospitales universitarios

La Planta Incineradora es el resultado de la incineración de desechos de diferentes dispositivos petroquímicos. En esta tarea, deseamos quemar todos los desechos resultantes de los dispositivos petroquímicos y, además, producir vapor de alta tensión a partir del calor producido por la planta de calefacción.
En el resultado inicial, los residuos de la industria petroquímica se acumulan y también se trasladan al tránsito y, además, se establecen centros en varios tipos. Las alimentaciones de entrada de la planta de calefacción se enumeran a continuación en la tabla:

Los proveedores de incineradores de centros de salud, las corrientes de desechos de dispositivos petroquímicos se acumulan y, además, se mantienen en el camino y también en las instalaciones de organización.
Tanto en Path como en Planning Facility se debe tener en cuenta la demanda de un laboratorio.
En este centro, los residuos se identificarán en 2 grupos:
–– – –– No apto para quemar
– – Residuos que se pueden revertir a la petroquímica.
Los desechos apropiados se reconocen directamente en ambas categorías: –– – Los desechos de entrada al horno rotatorio, consisten tanto en sólidos como en fluidos de desecho.
–– – – Los residuos de entrada al horno fijo, incluyen tanto fluidos limpios como también gases.
Todos los desechos fuertes deben trasladarse al foso del área de almacenamiento desde Transporte junto con la Clasificación. La fosa del espacio de almacenamiento de residuos sólidos es la entrada del horno rotatorio.
Todos los desechos líquidos deben ser mantenidos y mantenidos tanto en tránsito como en disposición. Todo el espacio de almacenamiento, así como las herramientas de estabilización o el centro, deben tenerse en cuenta.
El requisito de capacidad de almacenamiento y estabilización se debe considerar en función de las peores circunstancias (apagado).
Normalmente, la planta de quemadores contiene 2 trenes similares (la capacidad de cada tren es del 100%). Cada tren contiene un horno rotatorio y un horno tratado.

учреждение здравоохранения для плавления опасных отходов, а также химикатов

использование в больнице для сжигания опасных отходов, а также химикатов, минимальная производительность 300 в час. Я буду продавать своему клиенту ?. Ниже представлена информация, которую мне дали, и больше ничего. Горелка для больниц для использования с профессиональными отходами в соответствии с требованиями мирового экологического менеджмента. Производительность не менее 300 кг / час, газовая разгрузка, футеровка из огнеупора, дымовой вал, а также защита от дегустации. Минимальная температура 1100 градусов Цельсия. Устройство для сжигания отходов 500 кг в час. работа по размещению медицинских отходов в больницах. Просто хочу оценить различные типы установок для сжигания медицинского мусора. Нужна вся информация по системе 300 кг в час. доступность. функциональные затраты с использованием дизельного топлива (различные другие). отходы – это клетки человека. А у нас 10 кг каждый день; нам требуется горелка для медицинских отходов. Мощность сжигания: 50 кг в час (обычная мощность согласно медицинским отходам). пожалуйста, присылайте информацию о ценах на каждую из моделей крематориев для домашних животных. Что касается установки для сжигания газа, обратите внимание, что топливо для установки для сжигания
будет газ. Ведь газ у нас фишка.

hospital incinerator manufacturers

SECTION V

 

  • TECHNICAL SPECIFICATIONS OF THE INCINERATOR

 

  • General Description

 

The plant must have four distinct sections that demonstrate three principles of turbulence, residence time and temperature retention. The regulated sections may include but not limited to:

 

  1. Overall plant layout
  2. Feed chamber/charging
  3. Primary combustion chamber
  4. Particulate scrubbers
  5. Acid gas
  6. The stack/chimney.
  7. Minimum capacity of primary chamber = 10cubic meters
  8. Burn rate (rate of waste incineration) = 10 kg per hour
  9. Should have a full width counterbalance loading door allowing easy access to the main chamber for loading and removing ash.
  10. The INCINERATOR should be NEMA approved in accordance with Environmental management and coordination (Waste management) Regulations of 2006.

 

  • Scope Of Work

 

The work specified in the contract will include.

 

  1. Supply, install and commission an incinerator as provided   in the technical specifications

 

  1. Provision for adherence to OSHA and other statutory requirement relating to Health and Safety of workers during execution of the works covered in this

 

  1. Assessment and preparation  and construction of  a standard incinerator shed with one waste  storage room  ( see the design )

 

  1. Provision of operation and maintenance manuals and drawings complete with maintenance schedule and

 

  1. Fuel oil storage tank- Mild steel 1000 liters capacity

 

  1. Onsite training for operation and maintenance

 

IMPORTANT

To enable the Employer undertake conclusive evaluation of the tender, tenderers are requested to submit with their offers the detailed specifications, drawings and catalogues with Commissioning and maintenance instructions for the Incinerator they intend to Supply, install and commission.

Tenderers who fail to comply with this requirement fully shall have their tender rejected.

 

  1. TECHICAL SPECIFICATIONS OF THE INCINERATOR

 

3.1  Feeding and Charging

 

Controlled hygienic mechanical feeding that does not negatively influence the air temperature in the primary and secondary chambers of the incinerator shall be used.

 

  • Primary Combustion

 

  • This chamber should be equipped with burners that use low sulphur
  • The chamber should ensure a minimum exit temperature of 850 degrees
  • This unit should operate at over 1100 deg C to ensure complete
  • This chamber should be equipped with burners that use low sulphur
  • Heavy-duty steel casing
  • High quality refractory lining and insulation
  • Large full size top load door and liquid retention
  • 1 x oil fired ignition burners operated on/off

 

 

  • Secondary Combustion Chamber (After burner)

 

  1. Heavy-duty steel casing
  2. High quality refractory lining and insulation
  3. 1 x oil burner
  4. Should be fitted with burners that use low sulphur
  5. Ensure secondary air supply is controlled.
  6. Ensure residence time is not less than two seconds.
  7. Ensure that the gas temperature as measured against the inside wall in the secondary chamber and not in the flame zone is not less than 1100 degrees
  8. Ensure the emitted oxygen content of the emitted gases is not less than 11%
  9. Ensure both primary and secondary combustion temperatures are maintained until all waste is completely

 

  • Particulate Removers

A mechanical particulate collector must be incorporated after secondary combustion chamber for removal of particulate pollutants entrained in the flue gas stream. The particulate collectors may include any of the following or a combination thereof:

 

  1. Cyclone separator
  2. Electrostatic precipitators
  3. Fabric filters

 

  • Chimney/Stack

 

  1. The chimney should have a minimum height of 10 meters above ground level and clear the highest point of the building by not less than 3 meters for all The topography and height of adjacent buildings within 50 meters radius should be taken into account.
  2. The chimney should be visible to the operator from the feeding

 

  1. The minimum exit velocity should be 10 meters per second and at least twice the surrounding wind speed (Efflux velocity = wind speed x 2) whichever is higher to ensure no down washing of exiting
  2. The point for measurement of emissions shall be

 

  • Instrumentation

 

  1. Instrument for determining the inside wall temperature and not burner flame temperature must be provided for both primary and secondary
  2. An audible and visible alarm must be installed to warn the operator when the secondary chamber temperature drops to below the required
  3. A carbon monoxide and oxygen meter/recorder should be
  4. A smoke density meter/recorder should be
  5. A solid particulate meter/recorder should be
  6. Any other instrument that may be considered

 

  • Location / Siting of the Incinerator

 

  1. a) The incinerator must be sited in accordance with the relevant local municipal authority planning regulations and the topography of the site must be compatible with premises in the

 

  • Emission Limits

 

  1. Combustion efficiency (C.E) shall be at least00% where C.E = %Carbon dioxide x 100 / [% Carbon dioxide + carbon monoxide]
  2. The temperature of the primary chamber shall be 800 +/- 50 degrees centigrade
  3. The secondary chamber gas residence time shall be at least 1 second at 1050 +/- 50 degrees centigrade with 3% oxygen in the stack
  4. Opacity of the smoke must not exceed 20% viewed from 50 metres with naked
  5. All the emission to the air other than steam or water vapour must be odourless and free of mist, fume and
  6. A 99.99% destruction and removal efficiency (DRE) for each principal organic hazardous constituent (POHC) in the waste feed where DRE [ ( Win – Wout) /Win ] x

100 where Win = mass feed rate of the POHC in the waste stream fed to incinerator and Wout = mass emission rate of POHC in the stack prior to the release to the atmosphere.

  1. The average dioxin and furan concentration in the emission should not exceed 80mg/m3 total dioxins and furans if measured for a period of 6 to 16

 

  • Ease of Use

 

  1. Auto
  2. No pilots to
  3. Automatic control and temperature monitoring
  4. Built-in skid facilitates placement

 

  • Fuel Efficiency

 

  1. Rapid incineration means low fuel

 

  1. Up to 20kgs per hour (dependant on application).
  2. Thick refractory lining rated to 1400 deg C in main chamber retains heat, increasing

 

  • Quality Built to Last

 

  1. Heat resistant 3mm
  2. Stainless steel

 

  • Key Features

 

  1. Low running and maintenance costs
  2. Fully Automatic and simple to operate control panel
  3. Afterburner Preheat
  4. Incineration Temperatures in Excess of 900 degrees C
  5. 3 mm Steel Casing and Fully insulated
  6. Dense Refractory Concrete Lining Rated to 1400 degrees C
  7. Solid Hearth to Allow Maximum Burnout
  8. Large Top Opening Lid For Easy Loading
  9. Stainless Steel Flue as standard
  10. 12 Months or 1000 hours
  11. Optional Stainless Steel Casing
  12. Heat Recovery System option

 

3.13 Fuel and Capacity  
1. Low sulphur fuel
2. Capacity (Cubic Mtr) .10
3. Average Capacity 40kg
4. Fuel Consumption (ltrs / hr) 3

 

  • External Dimensions

 

1. Length (mm)               735  
2. Width (mm)                500
3. Height Incl. Flue (mm) 1960
4. Door Opening (mm) 325 x 325

 

  • Internal Dimensions

 

1. Length (mm) 620
2. Width (mm) 390
3. Height 500

 

  • Operation

 

  1. Minimum Operating Temperature 950
  2. Maximum Operating Temperature 1320

 

 

3. Burn rate per hour 5-20kgs
4. Temperature Monitoring Available

 

 

  • Particulate Removers

 

 

A mechanical particulate collector must be incorporated after secondary combustion chamber for removal of particulate pollutants entrained in the flue gas stream. The particulate collectors may include any of the following or a combination thereof:

 

  1. Cyclone separator
  2. Electrostatic precipitators
  3. Fabric filters

 

  • Chimney /Stack

 

 

  • The chimney should have a minimum height of 10 meters above ground level and clear the highest point of the building by not less than 3 meters for all The topography and height of adjacent buildings within 50 meters radius should be taken into account.
  • If possible the chimney should be visible to the operator from the feeding
  • The addition of dilution air after combustion in order to achieve the requirement of these guidelines is
  • The minimum exit velocity should be 10 m/s and at least twice the surrounding wind speed (Efflux velocity = wind speed x 2) whichever is higher to ensure no down washing of exiting
  • Point for the measurement of emissions shall be

 

  • Control Panel

 

  1. Control of 2 burners
  2. Timer control 0- 12 hours
  3. Integral fan timer control
  4. Temperature and thermostatic control

 

 

 

 

 

 

 

SCHEDULE 2

 

 

NO: REQUIREMENTS SUPPLIER’S REMARKS
1. Experience

 

Previous experience in the supply, installation and commissioning of  incinerators

 
2. 1 Year Maintenance Contract  
3. Work rate

 

at least10kg per day

 
4. Design

 

Basic Plan design to Provide Overall plant layout. With Feed chamber/ charging, Primary Combustion Chamber. Secondary Combustion Chamber. Particulate Scrubbers, Acid Gas Scrubbers, The stack/ chimney.

 

Fuel oil tank storage should be   Mild steel 1000 liters capacity

 

Chimney Height should be of 10 meters above ground level.

Housing facility with one waste storage room

 

 

Provide Housing designs with adequate cross ventilation

 

Chamber (Afterburner Maximum exit temperature should not be less than 1100oC

 
5. Standard control panel

 

Safety interlock, Fan Starter, Burner on/ off switch/door safety switch, Auto close down switch, temperatures control mechanism.

 
6. Combustion Chambers

 

Primary Combustion Chamber Minimum exit temperature should not be less than 850oC

 

Secondary Combustion Maximum exit temperature should be not less than 1100oC

 

 

SECTION VII

 

PRICE SCHEDULE FOR GOODS

 

Price schedule for Supply, Installation, Testing and Commissioning of an incinerator for Turkwel Power Station

 

1 2 3 4 5 6
Item Description Unit of sale Quantity Unit price Total price
1. Supply, install, and commission the incinerator as specified. LOT 1    
2. Construct a standard incinerator housing facility as per the drawing and architectural notes provided  

LOT

 

1

   
4. Construct one  waste  storage  room (provide specs on room size, construction material etc) LOT 1    
5. Supply / adhere to  the requirement of OSHA 2007 act

49,50,51,60,61,77,78,79,80,81,100

LOT 1    
6. Onsite training of Operation and Maintenance staff. LOT 1    
7. All the key Spares (Attach a separate List) LOT 1    
8. Supply and install 1000 liters Fuel oil storage tank and its secondary containment with Diesel oil level indicator and necessary piping with valves for visual checking of fuel level. LOT 1    
9. Supply of Operation and Maintenance Manuals.  

LOT

1    
10. All other items not specified but necessary to complete the Installation.   A separate list of these items to be attached.  

LOT

1    

 

 

11. Fencing of  a compound  of 10 meter length  by 10 meter  width   using Concrete  poles  high Gauge mesh wire , and a lockable gate. (Indicate size and design of gate) LOT 1    
  Sub Total        
           
  Discount  (%) if any        
  Applicable Taxes and Duties        
           
  Total Cost in Kshs        

 

animal incinerators for sale

SMART ASH INCINERATORS FOR THE DISPOSAL OF HAZARDOUS WASTE
?    Quantity: 20 units
?    The Incinerator works with a 55 gallon open ended steel drum
?    The unit operates without fuel and used only 120v or 220v electricity for the blowers
?    Unit is capable of burning oil contaminated waste and medical wastes with a moisture content of 0 to 15%
?    Each unit is supplied with two steel drums, so that a spare is available
?    Each unit to be supplied with recommended spare parts
?    Warranty – minimum 12 months from receipt and acceptance
?    Instruction manuals to be provided in French and English

HAZARDOUS WASTE TO BE INCINERATED

Hazardous Solid Chemicals
Different types of combustible solids, used textiles, grease and toner cartridges, chemicals for water purification and  photographic consumables, and plastic material, empty metal/ plastic cans that still contain remnants of hazardous materials, oil absorbent

Hazardous Liquid Chemicals
Mainly different types of Acid, Paint, Varnish, White Spirit, Aromatic-Less Solvents, Synthetic Liquid For Brake Systems, Aircraft De-icing Liquid, Hydraulic And Compressor Oil, Freon used in some older refrigeration units, Insecticide Liquid/Spray, Air Refresh Spray and other similar chemicals

Contaminated Fuel
Mainly diesel or gasoline contaminated by water or solvents

Used and/or Contaminated Oil
Used motor oils and/or mineral oils unfit for their originally intended use. Mainly motor/gear box oil (approx. 80%) contaminated by a  mixture of white spirit and acetone (approx. 5%) hydraulic liquid (approx 5%)

Contaminated Water
Waste oils/water, leaches, hydrocarbons/water mixtures, emulsions and leachate

Contaminated Soil
Soil polluted by oil fuel of chemicals,
Soil polluted that has to be recycled in landfill,
Soil treated and replaced on site

Oil Contaminated Solids
Rags, absorbents, cardboard, oil and fuel filters, air filters are not considered as hazardous materials

Electronic Waste
Waste electrical or electronic appliances or assemblies, including printed circuit boards containing toxic material and/or heavy metal and/or emitting low radiation

Used Battery Cells
Dry battery, ups battery or other types unsorted waste batteries/battery cells, containing materials that are hazardous

Used Lead Acid Batteries
Waste lead acid batteries, drained/ un-drained and whole or crushed

Hazardous Medical Waste
Clinical and related waste arising from medical, nursing or similar practices and waste generated in clinics during the investigation or treatment of patients (bio hazard)

Expired Drugs Solid
Waste pharmaceuticals, drugs and medicines, including sensitive medicines

Expired Drugs Liquid
Waste liquid pharmaceuticals, different type liquid chemicals for treatment, medical grease and paraffin based expired medicines

Expired and/Or Contaminated Food
Spoiled fresh food or unusable meal ready to eat meals (MRE’s) dry food

Medical waste incinerator 100kgs Model TS100

incinerator manufacturer,medical incinerator,small scale incinerator,oil fired incinerator

Items/Model

TS100

Burn Rate

Average 100 kg/hour

Feed Capacity

Average 200 kg/feed

Control Mode

PLC

Combustion Chamber

1200L

Internal Dimensions

120x100x100cm

Secondary Chamber

600L

Smoke Filter Chamber

Yes

Feed Mode

Manual

Voltage

220V

Power

0.7Kw

Oil Consumption (kg/hour)

14–28

Gas Consumption (m3/hour)

10–32.2

Temperature Monitor

Yes

Temperature Protection

Yes

Oil Tank

200L

Feed Door

80x60cm

Chimney

10Meter

Chimney Type

Stainless Steel

1st. Chamber Temperature

800-1000

2nd. Chamber Temperature

1000-1200

Residency Time

2.0 Sec.

Gross Weight

6000kg

External Dimensions

260x150x180cm



HICLOVER – Medical Environmental 


 

Waste Incinerators
Medical Waste Incinerator
Pet Animal Cremation
Solid Waste Incinerator

Tel:  +86-25-8461 0201   
Mobile: +86-13813931455(whatsapp/wechat)
Website: www.hiclover.com  
Email: [email protected]
Email: [email protected]  
Nanjing Clover Medical Technology Co.,Ltd.

 

2020-04-06