The other day in the waste incineration plant



Recently a dream came true for me. I had the opportunity to participate in a guided tour through the waste incineration plant in Cologne. That may seem strange. Sometimes I catch myself when I get stuck on documentary programs about recycling methods in the (rare) zapping through the TV channels. Obviously this topic fascinates me.

The BVMW (Federal Association of Medium-Sized Enterprises) invited to a lecture on the topic of generation Y. Host and the venue was the waste recycling company in Cologne, AVG, which offered additionally a guided tour through their waste incinerator. Since I am also very interested in the topic Generation Y, I could kill two birds with one stone.
In a small group, we were led by the spokesman of the AVG through the various sections of the waste incineration plant and the procedures were explained in detail. Initially skeptical, because in previous years there was so much negative about this facility (excessive construction costs, lack of capacity), the mood among the participants changed gradually into fascination.

To clarify: It’s just about waste. Not about recycle materials such as paper, plastics, recycled glass or compostable organic waste.

Precision and cleanliness

What I noticed during the tour: In the plant, each step is carefully considered, it is worked with great precision. And even if that sounds paradoxical: it is squeaky clean! Only in the hall where different wastes are mixed on conveyor belts, there is the typical smell of rubbish, but also not as bad as originally expected.

Amazing for me: I did not know that by using residual waste a really large amount of power is generated. And reassuring for me: resources are won even from the last drop: metal, material for road construction, plaster in good quality. The proportion of what is factually left and actually not recycled, seems negligible to low.

From waste to electricity – the process in detail

The residual waste incinerator in Cologne was put into operation in 1998 and is one of the most modern and best facilities in the world. It processes what has landed in the residual waste after the separate collection of private households, as well as the remains of sorting from mixed building and industrial waste.

Much of the waste is shipped by rail. The railway containers are loaded in two waste transfer stations in the city of Cologne and together have a capacity of approximately 250,000 tons per year. The remaining waste is brought by truck.
A special feature of the Cologne residual waste incinerator is the integrated treatment of the waste in a treatment room. Residues from sorting and residues from the domestic and bulky waste are first distributed to the daily waste bunker on separate chambers. The bulky waste is pre-sorted and crushed. Only the non-recoverable components are processed in the incinerator.

The household waste is sorted in a perforated drum to size and then passes on large conveyor belts so-called magnetic seperators. They remove ferrous scrap. A second ferrous metal deposition as well as an automatic non-ferrous deposition take place after combustion.

Even commercial waste residuals are delivered to the Cologne plant. They have been processed previously in external sorting, so they can be added directly to the domestic and bulky waste. The various waste streams are mixed thoroughly, because this homogenization ensures a high quality, a uniform as possible burnout and a good quality ash.
From the huge hall of the conveyor belts the waste enters the so-called residual waste bunker. Here it is stored a while until enough moisture has dissipated, so that it can burn well. By means of permanent temperature and humidity indicators it is controlled, in what condition the waste is. With large gripping cranes the waste is rearranged and finally placed in the kiln. The garbage gripper fill four huge funnels. The waste comes from here in four independently powered boilers that operate around the clock. The waste moves on roller grates through the boiler. And there it burns. At an unimaginable heat of 1,000 to 1,500 degrees Celsius. The respective “new” waste ignites from the already burning garbage. So no additional external energy is required for the combustion process. The combustion takes place after the DC principle: The burning of waste and the waste gases move in the same direction through the “hot flame” at the end of the grate. This procedure ensures that the destruction of pollutants such as dioxins and furans are already done in the combustion chamber.

From waste is made power for 250,000 people

And here is the highlight. The heat produced during combustion is used. On the one hand, to heat the nearby Ford plant. But this is just a nice side effect. The majority of the heat is converted into electricity by generators. And even that much that the power consumption of 250,000 people can be met. The waste incineration plant Cologne is thus basically a power plant and supplies a quarter of the city of Cologne with electricity. That sounds awesome. And since you could get the idea that it is not so bad when so much garbage is produced – as it is used so well …

After combustion bottom ash, hot exhaust gas and residues remain. These substances are largely used again useful: The ash is cooled with water and stored in an ash bunker before it is processed in a bottom ash treatment plant and then utilized in road, landfill and landscaping.
The hot exhaust gas is used for power generation. It heats preheated water to steam, which meets at a temperature of 400 degrees Celsius and a pressure of 40 bar to a turbine. This drives the downstream generator with which is produced electric power. For own use only a small part of the energy is needed. The greater part is given in external power supply networks. The amount of energy generated in the incinerator is enough to power more than 100,000 households.

In the combustion and the subsequent exhaust gas purification residual substances such as dust and salts remain as well as ashes from the boiler. These materials are collected and used as backfill material for the backfilling of salt mine tunnels. Gypsum is also a waste material, which is obtained as a reaction product in the exhaust gas purification and has building material quality.

Emission control: the exhaust gases are almost completely neutralized by the method used at the Cologne incinerator. There is no waste water, as well as the legal requirements are clearly undercut. As a neutral auditor, the county government gets the actual exhaust gas readings permanently by direct line.

Rethinking at waste management companies

After the guided tour, I had the opportunity to talk to the press officer of AVG. In this conversation it became clear how much the thinking has changed in the field of waste management in recent decades and years. While during the 1960s to the 1990s garbage was piled up completely unsorted in landfills and then forgotten, in the new millennium they have recognized the value of the waste. Climate change and CO2 emissions have long pushed as important issues in focus for the residual waste processing. The heat generated during combustion is converted into electricity. Resources are regained, as far as is technically possible. Especially metal, plastics and wood. The recovered plastic from residual waste is used for example as fuel for cement plants.

Waste incineration plant are nowadays equatable to power plants, even if the fuel value is not quite equivalent to the conventional fuels such as coal, oil and gas. As more and more municipalities have come to generate their own electricity by means of residual waste incineration, the major electricity providers get in significant difficulties.

At the end of the tour I was really impressed. That what is put in the residual waste in private households plus the commercial waste is, after all, still god to supply 100,000 households with electricity in Cologne.

And at the same time it’s scary, what incredible tonnes of waste we produce. Yellow and blue ton even come on top of that.

Consumer society provides garbage

Waste incineration plants generating electricity for us and making us less dependent on fossil fuels, are the logical consequence of our consumer society. But incinerators are not built primarily to generate electricity. But to become master of the mountains of waste that we produce continuously as a consumer society. Fortunately, with modern incinerators, a way has been found to make up the stinking problem a clean thing. But the cause, our consumption, is the real problem.

For the operators of the incineration plant, it is essential that enough waste is delivered. Garbage is their product. The more they can get, the better for the system’s capacity. For then it will work cost-effectively, which in turn has a positive impact on the urban garbage fees. Not all incinerators in Germany are so well utilized as in Cologne. Since waste is added from adjacent areas.

But the consumer society provides these masses of garbage. Goods are produced in large quantities, purchased, used or consumed and eventually discarded. The 2aste incineration plant gets food – in 2013 there were 707,000 tons in Cologne. And provides us even with power (282 million kWh in 2013 in Cologne). Actually a perfect cycle, so one might think. If not for this “but” would be. Because our conventional consumption goes at the expense of other countries, to the detriment of the environment, fair working conditions; Resources are wasted, the transport around the globe has impact on the climate, production facilities in the Far East poison the local environment and so on.

Well, I live in Cologne, a big city, where certainly only a small proportion of residents think about trash, disposal or even waste reduction and also practice this. That may be a negative point of view, but I think it is realistic. The average normal citizen does not necessarily ask the question what is actually happening to what he throws away in the course of a year. All the more it is interesting to follow the different paths. My next wish is to visit a recycling plant for plastics.

Waste incineration and waste seperation versus waste prevention

Waste separation was yesterday. The latest approach is waste prevention. In its most distinct version it is called Zero Waste. No waste. So far there are only a few pioneers, whose reports and videos I read and watch with interest. And at the same time I wonder how to implement this in a normal big-city life. It starts with the fact that – even if you use a togo box, which is compostable, then you do not know where to dispose of it along the way. So take it home and put it in the compost bin? Would everybody do that?

I think it’s great if it is possible, to be master of the situation (immense amounts of waste) through a well organized disposal system and beyond even to convert this residual waste to a large extent into energy, ie electricity and heating. There is at least a huge improvement as against the stinking landfill from earlier, in which everything was thrown into a pile and then covered with the cloak of silence. The next step must be, to reduce the amount of waste in total. And this will not be possible just by the civil society. Here politics and economy are asked to create the right framework and to set the practical implementation in motion.

by: http://blog.upcycling-markt.de/en/blog/muellverbrennungsanlange-waste-incineration-plant.html



Incinerator Primary Combustion Chamber



HICLOVER now offer a full range of containerized incineration systems, placing us at the forefront of the latest transportation and industrial 
trends. Containerization enables immediate waste management as the units are pre-assembled and pre-installed.
Containerization is the most feasible and viable option in contrast to the construction of on-site facilities and housing structures, 
eliminating the man power and costs involved. The system has the added benefit of total mobility (both local and international), and is ideal 
for military and civil camps and remote locations where infrastructure is scarce.
Incineration is the most obvious solution for total destruction of municipal waste, avoiding all the direct and indirect risks associated with 
other disposal methods.
Incineration perfectly fits into a trend of treating waste in a safe way, and if possible, at the same place where it was generated to avoid 
cross-contamination risk and to keep waste treatment costs at acceptable level.

WWW.HICLOVER.COM|Waste Incinerators |Auto Roll Air Filters

Nanjing Clover Medical Technology Co.,Ltd.

Tel:  +86-25-8461 0201   
Website: www.hiclover.com  
Email: [email protected]
Email: [email protected]  



Central Australia’s animal graveyard



The figure was revealed in the Alice Springs regional waste management facility report for October.

The dead pet you asked the vet to dispose of will end up buried in landfill, in most places across the country, and Alice Springs is no different.

“It’s a combination of horses, dogs, cats, pigs, any animal that dies,” said Alice Springs council technical services director Greg Buxton. “Road kill, kangaroos and that, the rangers pick them up, and you’ve got to dispose of them somewhere hygienic. So we put them at the back of landfill.”

The facility is on track to exceed last year’s total, with 3.7 tonnes deposited in the first quarter of this financial year.

Mr Buxton said most regional councils across the country dispose of dead animals in landfill.

“In the bigger cities they have an incinerator type setting where they cremate them, whereas we don’t have an incinerator here,” he said.

by: http://www.news.com.au/national/northern-territory/central-australias-animal-graveyard/story-fnn3gfdo-1227123002725



MEDICAL WASTE INCINERATOR (50 C 60kg/hr)



Medical Waste Incinerator, 50 to 60 Kg/hr
Support Health Sector Support Project
Point of Installation (Hospitals) Moi Voi, Makindu, Maragua, Eldama Ravine and Isiolo District Hospitals
1.    General Description
Supply, delivery, installation and commissioning of a medical waste incinerator suitable for disposal of Medical, General and Pathological waste in a safe and clean environment.  The unit shall consist of two chambers and operate on the principal of controlled air and temperature. The unit shall consist a particulate remover (scrubbers) as stipulated in waste management regulations, 2006 (Legal notice NO. 121 of 29th September, 2006).  The Unit shall be fully automatic and controlled by an automatic electronic controlled system except loading system which shall be manual.  The unit shall be capable of incinerating between 50 to 60 kg of solid medical waste per hour.  It shall be constructed from mild or aluminized steel lined with refractory material.
Main unit
Application For incineration, general and pathological
Capacity   50 C 60 kg/h burn rate
Type Two  combustion chambers type; primary  and Secondary, controlled/forced combustion air type with a flue gas emission scrubbing unit
Operating time                Minimum 8 hours daily
Operating temperature     From 850 0C to 1200 0C, Automatic controlled
Residual Ash                    5 to 10%
    3.2     Primary Chamber
Construction Constructed from heavy duty mild or aluminized  steel Or
equal and approved equivalent
Insulation material            Refractory material lining similar or equal to calcium 
Silicate and hot face combination of heavy duty brickwork
Internal Construction        Fixed hearth type complete with gratings, concave bottom
and charging door, lined with refractory material
Charging Door                   Suitable for manual loading of wastes and with smooth 
Dear seal equivalent of Ceramic seals with hinges.
Door Lock                          Automatic, Electric type
Ash removal door    Provided, for removing resultant bottom ash leftovers                              from the Primary chamber
Gratings   Provided
Loading Manual loading of waste
Primary Burner                        Fully automatic, with fuel, temperature and speed controls with ignition system, flame detector, Air fan complete with safety features, flame failure,  Diesel fired fuel injector type and Flange mounted                                                                                                    
Blower Provided. For supplying excess combustion air through the distribution system with speed control system
Temperature Minimum exit 850 0C
Observation port To be provided with protective glass type
Construction   Constructed from heavy duty mild or aluminized steel or equal and approved equivalent
Insulation Refractory material lining
Combustion Temperatures        Above 850 0C, controlled electronically
Gas residue or retention Time       > 2 second at minimum 850 0C
Secondary Burner                    Provided, Diesel fired, fully automatic, with fuel, temperature and speed controls, With ignition system,                                                                  Flame detector, Air fan, Complete with safe
ty features, flame failure Diesel fired fuel injector type.                                                                  Flange mounted
Ejector Provided, Venturi type, for cooling the flue gases
Combustion Air Fan Provided for supplying combustion and creating a negative drift and turbulences
Temperature Maximum  1600 0C


An Unexpected Ebola Infrastructure Problem: Waste



Patients with this debilitating virus produce 440 gallons of medical waste daily, including instruments, gowns, gloves, body fluids, sheets, mattresses and more. That’s a substantial amount of medical waste in any situation, but it’s especially daunting in this case because it needs to be disposed of extremely cautiously, to avoid the risk of spreading infection. What do you do with a problem like Ebola waste? Because you don’t want to toss it in the garbage.

Somewhat surprisingly, says Bausch, the United States actually faces bigger problems when it comes to safely disposing of Ebola waste, which is simply burned in large pits in Africa: “In the United States, of course, we are somewhat beholden to higher tech solutions, which in some ways are a little bit more problematic in terms of treating all that waste, and we need autoclaves or incinerators that can handle that sort of thing. It’s not the actual inactivation that’s particularly difficult; it’s just the process of getting the waste from, of course, the frontline of care and interaction with the patients safely to the place where it can be incinerated or autoclaved.”

The problem in the United States is ironically compounded by the increased access to medical care, and the higher quality of medical services, available. In the United States, patients are treated by medical teams with access to a huge volume of supplies they use for protection, including masks, gowns, booties, and gloves, along with sanitizers and other tools. Moreover, patients receive extensive medical interventions that generate waste like needles, tubing, medical tape, empty IV bags, and more. The very care that has helped most of the handful of Ebola patients in the United States conquer the disease has contributed to the huge amount of waste generated, highlighting a critical hole in U.S. medical infrastructure — while African hospitals may have lacked the supplies and personnel needed to supply aid to Ebola patients, they’re at least prepared to handle the waste.

The CDC just issued guidelines to help clinicians and administrators decide upon how to handle Ebola waste, but The New York Times notes that many facilities don’t have the autoclave, and incinerator, capacity to handle medical waste on this scale. Some states prohibit the burning of medical waste altogether, or have barred incineration of Ebola waste, leading to the transport of waste across state borders to facilities that can handle it, which poses its own risks; with every mile added to transport, there’s a greater risk of spreading disease to previously unexposed communities.

Surprisingly, defenders of burning the waste come from surprising corners. Environmentals like Allen Hershkowitz, National Resources Defense Council senior scientist, point out that: “There’s no pollutant that’s going to come out of a waste incinerator that’s more dangerous than the Ebola virus. When you’re dealing with pathogenic and biological hazards, sometimes the safest thing to do is combustion.”

The argument in defense of incineration can be bolstered by the fact that medical waste companies specialize in high-efficiency incineration with equipment designed to minimize and trap byproducts of combustion, reducing overall pollution considerably. Fears about Ebola, rather than genuine environmental or public health concerns, are driving the decision to push against incineration of ebola waste in many regions, but eventually, the United States is going to have to face facts: The mounting waste that accumulates in facilities where Ebola patients receive treatments needs to be disposed of safely, and promptly.

 

by: http://www.care2.com/causes/an-unexpected-ebola-infrastructure-problem-waste.html



Medical Waste Incinerator: Essential Medical Waste Disposal Services Provided By Meda Send



Medical Waste Removal Companies Medical Waste Service Suggestions There are different types of wastes that people need to be conscious about in order to avoid exposure to this waste that may cause health illnesses and diseases. One of the most dangerous types of waste that people need to get rid of is hazardous wastes. These are the type of wastes that completely pose potential or substantial threats to people particularly to public health and to the environment. These wastes are also known as special wastes since they cannot be quickly disposed compared to other types of wastes.

Thus, in order to relieve all the worries of the people regarding this matter Meda Send offers hazardous waste disposal that could help medical facilities. They are providing cost-effective as well as safe services that could easily and effective disposed your hazardous waste. They are very consistent in giving safe as well as environmental-friendly services to the people in order to disposed common existing hazardous waste in medical facilities. They are the best company that would lend your medical facility hazardous waste disposal plan that would be effective towards your aim for a healthy and safe environment for the people.
Pathological Waste Definition

Hazardous wastes are those chemicals and medicines that are toxic and infectious that can effectively affect the health of the people upon exposed. These may also be laboratory medicines which are used by doctors in aid for harsh and severe diseases and illnesses of patients. Disposing these hazardous waste would not be a difficult task since Meda Send would be your help in this matter. They are going to provide medical facilities containers in colored red covered by red plastic where they can put their hazardous wastes. They are also giving medical facilities adequate time in collecting all the hazardous wastes that may be found in their place. This is essential before allowing the pickup truck of the company to get your collected hazardous wastes.

They are very much concern on the health of the people inside and outside of their medical facility hence they wanted to make sure that they would not be exposed and be inflicted with the toxins and other harmful chemicals coming from this hazardous waste. Since Meda Send is always available, medical facilities would always have an assurance of a quick disposal of waste particularly when there are already huge quantity of hazardous waste in their place.
medasend.com Sharps

Hazardous waste disposal could be an easy task for all medical facilities particularly if they are going to seek any of the waste management disposal services of Meda Send. Don’t miss the opportunity to avail any of the services offered by Meda Send for a healthy and safe environment. This would always guarantee that you will have a healthy environment that is free elements that pose health risks.

Most people know that there is a large amount of medical wastes that are being produced by most of the medical facilities like hospitals, clinics and many other health facilities each day. These wastes need to be properly collected, transported, segregated, and disposed to its proper places and condition. Although some medical facilities are considered to be proficient and knowledgeable in disposing their wastes, they still need to seek a company that could guide them and help them on how they are going to dispose their waste properly particularly when instances that they can no longer handle proper medical waste in their place.

That is why Meda Send would be an effective answer to what medical facilities are greatly in need of in terms of their wastes and garbage each day. They are one of the highly recognized companies all over the world that is highly specialized when it comes to healthcare and proper medical waste disposal. They are not just aiming to help people in managing their waste sine they also aim to provide a healthy community free from diseases and illnesses that may be due to improper disposal of waste.
medasend.com Posts

Meda Send is very committed and devoted in giving waste services to all the people. They can effectively handle medical disposal needs of medical facilities with their speed as well as accuracy. They are very effective in providing the people waste management services which aims for a healthy environment not only covered by the people who are inside the medical facility but also with all the people in the community. With the help of medical waste disposal services of the company, people are guided with the proper waste management they need to do. This is not only good for nurses and doctors but for all the people as well.

They are given greater chance to be well-equipped with the proper segregation of waste. This is very important to get rid of risk since these wastes are considered to be harmful to people and to the environment. They are taught on the right place where to put their waste. This is through allowing them to segregate their waste in a red plastic. Medical waste disposal of the company is known to be very effective and efficient since they are providing consistent type of truck pickup grid making the people feel at ease in scheduling medical waste pickups. They are also available 24/7 hence they make sure that waste compliance needs of the people are given high importance that the company is not taking for granted.

So, for medical facilities that are rendering services to large or small group of people, Meda Send could be one of the best companies that could give you safe and healthy environment that could cater the needs of the people towards a healthy and safe community to live.

by: http://ourbdspace.com/blog/34552/medical-waste-incinerator-essential-medical-waste-disposal-services-provide/



MEDICAL WASTE INCINERATOR (50 C 60kg/hr)



Medical Waste Incinerator, 50 to 60 Kg/hr
Support Health Sector Support Project
Point of Installation (Hospitals) Moi Voi, Makindu, Maragua, Eldama Ravine and Isiolo District Hospitals
1.    General Description
Supply, delivery, installation and commissioning of a medical waste incinerator suitable for disposal of Medical, General and Pathological waste in a safe and clean environment.  The unit shall consist of two chambers and operate on the principal of controlled air and temperature. The unit shall consist a particulate remover (scrubbers) as stipulated in waste management regulations, 2006 (Legal notice NO. 121 of 29th September, 2006).  The Unit shall be fully automatic and controlled by an automatic electronic controlled system except loading system which shall be manual.  The unit shall be capable of incinerating between 50 to 60 kg of solid medical waste per hour.  It shall be constructed from mild or aluminized steel lined with refractory material.
Main unit
Application For incineration, general and pathological
Capacity   50 C 60 kg/h burn rate
Type Two  combustion chambers type; primary  and Secondary, controlled/forced combustion air type with a flue gas emission scrubbing unit
Operating time                Minimum 8 hours daily
Operating temperature     From 850 0C to 1200 0C, Automatic controlled
Residual Ash                    5 to 10%
    3.2     Primary Chamber
Construction Constructed from heavy duty mild or aluminized  steel Or
equal and approved equivalent
Insulation material            Refractory material lining similar or equal to calcium 
Silicate and hot face combination of heavy duty brickwork
Internal Construction        Fixed hearth type complete with gratings, concave bottom
and charging door, lined with refractory material
Charging Door                   Suitable for manual loading of wastes and with smooth 
Dear seal equivalent of Ceramic seals with hinges.
Door Lock                          Automatic, Electric type
Ash removal door    Provided, for removing resultant bottom ash leftovers                              from the Primary chamber
Gratings   Provided
Loading Manual loading of waste
Primary Burner                        Fully automatic, with fuel, temperature and speed controls with ignition system, flame detector, Air fan complete with safety features, flame failure,  Diesel fired fuel injector type and Flange mounted                                                                                                    
Blower Provided. For supplying excess combustion air through the distribution system with speed control system
Temperature Minimum exit 850 0C
Observation port To be provided with protective glass type
Construction   Constructed from heavy duty mild or aluminized steel or equal and approved equivalent
Insulation Refractory material lining
Combustion Temperatures        Above 850 0C, controlled electronically
Gas residue or retention Time       > 2 second at minimum 850 0C
Secondary Burner                    Provided, Diesel fired, fully automatic, with fuel, temperature and speed controls, With ignition system,                                                                  Flame detector, Air fan, Complete with safe
ty features, flame failure Diesel fired fuel injector type.                                                                  Flange mounted
Ejector Provided, Venturi type, for cooling the flue gases
Combustion Air Fan Provided for supplying combustion and creating a negative drift and turbulences
Temperature Maximum  1600 0C


Another challenge: disposing of waste



A single Ebola patient treated in a U.S. hospital will generate eight 55-gallon barrels of medical waste each day.

Protective gloves, gowns, masks and booties are donned and doffed by all who approach the patient’s bedside and then discarded. Disposable medical instruments, packaging, bed linens, cups, plates, tissues, towels, pillowcases and anything that is used to clean up after the patient must be thrown away.

Even curtains, privacy screens and mattresses eventually must be treated as contaminated medical waste and disposed of.

Dealing with this collection of pathogen-filled debris without triggering new infections is a legal and logistical challenge for every U.S. hospital now preparing for a potential visit by the virus.

In California and other states, it is an even worse waste-management nightmare.

While the U.S. Centers for Disease Control and Prevention recommends autoclaving (a form of sterilizing) or incinerating the waste as a surefire means of destroying the microbes, burning infected waste is effectively prohibited in California, and banned in several other states.

“Storage, transportation and disposal of this waste will be a major problem,” California Hospital Association President C. Duane Dauner warned Sen. Barbara Boxer, D-Calif., in a letter last week.

Even some states that normally permit incineration are throwing up barriers to Ebola waste.

In Missouri, the state attorney general has sought to bar Ebola-contaminated debris from a St. Louis incinerator operated by Stericycle Inc., the nation’s largest medical waste disposal company.

Due to restrictions on burning, California hospital representatives say their only option appears to be trucking the waste over public highways and incinerating it in another state — a prospect that makes some environmental advocates uneasy.

Rules for transport

Under federal transportation guidelines, the material would be designated a Class A infectious substance, or one that is capable of causing death or permanent disability, and would require special approval from the Department of Transportation, hospital representatives say.

“These are some pretty big issues and they need some quick attention,” said Jennifer Bayer, spokeswoman for the Hospital Association of Southern California.

“We fully expect that it’s coming our way,” Bayer said of the virus. “Not to create any sort of scare, but just given the makeup of our population and the hub that we are. It’s very likely.”

The Ebola virus is essentially a string of genetic material wrapped in a protein jacket. It cannot survive a 1,500-degree scorching within an incinerator, or the prolonged, pressurized steam of an autoclave.

“The Ebola virus itself is not particularly hardy,” CDC Director Dr. Thomas Frieden said under questioning on Capitol Hill recently. “It’s killed by bleach, by autoclaving, by a variety of chemicals.”

However, CDC guidelines note that “chemical inactivation” has yet to be standardized and could trigger worker safety regulations.

Getting ready

California health officials recently tried to reassure residents that the state’s private and public hospitals were up to the task and were actively training for the possible arrival of Ebola.

“Ebola does not pose a significant public health risk to California communities at the present time,” said Dr. Gil Chavez, an epidemiologist and deputy director at the California Department of Public Health. “Let me tell you why: Current scientific evidence specifies that people cannot get Ebola through the air, food or water. … The Ebola virus does not survive more than a few hours on impervious surfaces.”

It was unclear whether California officials viewed the waste issue as a potential problem.

Although one-third of the state’s private hospitals and “a few” of its public hospitals reported to Boxer’s office that there would be problems complying with the CDC’s incineration recommendation, and others, a state public health official told reporters he was not aware of any conflicts.

Dr. David Perrott, chief medical officer for the California Hospital Association, said there was also confusion about whether infected human waste could be flushed down the toilet.

“Here’s what we’ve heard from the CDC: It’s OK,” Perrott said. “But then we’ve heard from some sources, that maybe we need to sterilize it somehow and then flush it down the toilet or you have to check with local authorities. It sounds maybe a little gross, but there is a real question about what to do with that waste.”

Overreaction?

Dr. Thomas Ksiazek, a professor of microbiology and immunology of the University of Texas Medical Branch, has said he believes there’s been a lot of overreaction about Ebola medical waste.

“There are other ways to deal with the waste; autoclaving would be chief among them,” Ksiazek said. “The problem is, most hospitals don’t use it for most disposable items. They’re quite happy to bag them up and send them to a regular medical disposal company.”

But Allen Hershkowitz, a senior scientist at the Natural Resources Defense Council, said incineration is simple and effective, and should be available to hospitals to help dispose of the mountain of waste.

Hershkowitz said states began to crack down on medical waste incineration years ago because materials that didn’t need to be burned were being sent to combustors and were emitting dangerous pollutants.

In this case of Ebola medical waste, he said California should reconsider its restrictions.

“There’s no pollutant that’s going to come out of a waste incinerator that’s more dangerous than the Ebola virus,” Hershkowitz said. “When you’re dealing with pathogenic and biological hazards, sometimes the safest thing to do is combustion.”

by: http://www.sfgate.com/news/article/Another-challenge-disposing-of-waste-5909413.php



County scraps plans for waste-to-energy incinerator



The Board of County Commissioners struck down plans Thursday for a regional waste-to-energy incinerator, opting to haul the county’s waste to a landfill with a short-term contract instead.

In a 3-2 vote, Commissioners President Blaine Young and commissioners Kirby Delauter and David Gray voted to kill the $471 million incinerator project by canceling the contract and related permits. Commissioners Paul Smith and Billy Shreve cast the dissenting votes to keep the project on the table while the county explores its options.

“It is absolutely no cost to the county to keep these options open,” Smith said. “To do away with these options is crazy.”

Terminating the project will not cost the county any money as the Northeast Maryland Waste Disposal Authority, a quasi-governmental agency that helps the county meet its trash disposal needs, will pay the $500,000 termination fee. Any remaining funds after this payment will be divided between Frederick County and Carroll County, which was once a partner in the project. These funds are from payments the authority has received from Wheelabrator after the service contract was executed in 2010.

However, Young said he saw no point in voting to keep plans for an incinerator, which would burn trash into energy, open since County Executive-elect Jan Gardner planned to scrap the facility after taking office Dec. 1.

“If the county executive-elect says terminate the project, what are you going to do within the next 30 to 60 days to convince her not to?” Young said.

County Attorney John Mathias said Gardner held the power to determine the fate of the incinerator project, not the County Council, if a decision was not made Thursday.

“I think you should terminate the whole thing,” Gardner testified in front of the board and roughly 100 people gathered at Winchester Hall, garnering some applause.

The board unanimously voted in favor of hauling the county’s trash to an out-of-state landfill for $50.95 per ton with a maximum five-year contract.

After considering five proposals, including three out-of-state landfills and two waste-to-energy facilities outside of Maryland, the commissioners narrowed down their options between two landfills with varying contracts.

Commissioners previously leaned toward the first option, which offered contracts extending 25 years at an average of $54.97 per ton, although that cost could escalate annually with the consumer price index and fuel prices. However, the board unanimously chose the second option, which Gardner also favored.

About 30 people testified in front of the board regarding the incinerator project, with a little more than half in favor of scrapping it and the rest advocating for keeping the project on the table to consider it more deeply.

“The incinerator is a waste of energy, a waste of resources (and) a waste of money,” Brunswick resident Ellis Burruss testified. “It would be good to not waste any more time on it.”

Other residents noted the proposed location of the incinerator, near Monocacy National Battlefield, would ruin the park’s beauty and tourism.

However, resident Greg Brown voiced his support for a regional incinerator, noting it was more environmentally friendly than the other options commissioners were considering.

“Even the best landfills … are at least three times more pollutant than a waste-to-energy facility,” Brown said.

Another resident said Europe has been building waste-to-energy facilities for years without the negative consequences that many have brought up.

Jim Warner, CEO of the Lancaster County Solid Waste Management Authority in Pennsylvania, pitched a proposal for hauling the county’s trash, but the commissioners decided to go with an undisclosed out-of-state landfill with a short contract.

“I was actually for this (incinerator project), but with the energy prices and Carroll County dropping out … I’m not,” Delauter said, echoing the sentiments of Young and Gray.

by: http://besttopics.net/link/214519_county-scraps-plans-for-waste-to-energy-incinerator-politics-and-government-frederick-news-post



hot medical waste disposing machine, Operation Condition: 8-16 hr/ day



hot medical waste disposing machine, Operation Condition: 8-16 hr/ day 
Control: Built-in data recording
Operating temperature: Incinerator 
/Primary Combustion Chamber
Primary Chamber: 900 – 1200 0C

Type: continuous loading, Top Loading
Capacity/Burn rate per hour: 250 -300 kg/hr 
Material:
External- 3 layers 
Internal lining:  a fire proof material of pre-fired refractory bricks with Aluminium lining, resistant to corrosive waste or gas and to thermal shock
Secondary 
Combustion 
Chamber:
Type: horizontal/vertical
Temperature:  1200- 1300 oC
Residence time of gases : >2 seconds
Ash Residue: <5% of original waste size
Ash Handling System: Both Automatic and manual removal of Ash. Must ensure removal/treatment of hazardous remnants of ash
Flue gas treatment   system : Capable of treating the flow of flue  gas as the incinerator is operating at its maximum capacity
Auxiliary device: Water level gauge, pressure sensor, PH sensor..etc 
Auxiliary device: Fuel cut-off device
Waste  feeding mechanism: Automatic pneumatic/hydraulic waste loading system or conveyor belt , capacity 650-800 L at a time                                                                                                                                      
Chimney (Stack):
Type: Vertical type
height:>7 meter’
Material: Fireproof cast, stainless steel
OUTPUT: 
GAS- SMOKELESS,ODORLESS 
ASH -Max <5% of original waste size
Reduction of Pollutant gas SO2, HCL, HF and line particulate
Emission standard:
WHO/ European
Test report for emission testing provided?
Heat exchange mode: Automatic

Accessories:  
All standard accessories for incinerator, including but not limited to loading system, heat exchangers, pollution control system, ash removal system, including ladder and oil tanker (2500litre capacity).
Operating Environment: 
The incinerator is capable to operate at the altitude of 2400mt above sea level. (according to the site conditions)
Power Requirement:
220 Vac single phase or 380 Vac three phase 4 wire system  50HZ   
Installation Testing and Commissioning :   to be conducted by certified or qualified personnel.  
Supplier shall provide the following documentation    
User (Operating) manual in English. 
Service (Technical / Maintenance) manual in English. 
Certificate of calibration and inspection from factory. 
Fast moving spare parts: Supplier is able to provide fast moving spare parts with quantities as described in the price schedule or their equivalent. 
Training: Supplier is able to provide training on operation, management and maintenance of incinerators.   
Warranty 
Comprehensive warranty for minimum 2 year. 
Maintenance Service during Warranty Period 
During warranty period supplier must ensure, corrective/breakdown maintenance whenever required. 
Supplier has a local agent or branch office in Ethiopia (please indicate the name and contact details of the agent) 
Supplier provides labor, lifting equipment and tools needed for the installation, testing and commissioning of the incinerator. The supplier will be responsible for the safety of its staff, workers and laborers during the installation, testing & commisssioning 
Able to provides all necessary information that would be used as an input for preparation of floor (platform) and room for the incinerator to be supplied such as the following; 
Lay outs (drawings) and  pictures of the incinerators to be installed 
 Length, width and height of incinerator,
 Area (length x width) for the floor (platform) and Length, width and height for roofing, for each type of incinerators to be installed 
Needs during the transport, installation, assembly, commissioning and operation of the equipment in terms of access points, available space to operate (inside and outside of the room), ways to get to the site where the equipment will be placed or any others. ; 
Technical Specifications (fuel consumption rate, weight, anchoring system, support points, etc.);
 Chimney specifications to be used for the roof design ( size, support needs, insulation); 
Considerations related to operation and Maintenance, for e.g., minimum available area to perform routine maintenance tasks and replacement of key parts that need to be changed more frequently; 
Any consideration/need of the incinerator while being operated that might impact the design of the room/shelter where it will be placed.
Other important information to be considered that can influence or impact the designing and building processes of the infrastructure for the incinerators, for example area dimension for other accessary parts like fuel tanker storage, if applicable, etc…. 
Delivery time (DAP, Addis Ababa) in weeks
Name of manufacturer including website of the manufacturer &/ supplier & country of origin