Medical waste incineration system


Medical waste incineration system of 300 kg/hr lost price with double gas (gas along with diesel) type, everyday 8-16 hrs treatment and also a stack altitude of 15 meter.Primary burning
i. The primary combustion chamber will be accepted as the crucial burning area;
ii. The marginal burning temperature of the main chamber will certainly not be a lot less than 800 levels C;

Secondly combustion
The home time in the 2nd chamber shall not be less than 2 secs;
The gas temperature as measured versus the inside wall in the 2nd chamber, not in the flame area, will certainly not be much less than as suggested in Lots 1-7;
Both the primary as well as the extra temperature level degrees will be protected till all the waste has actually been totally ignited;

Smokeshaft
The smokeshaft shall have a minimal altitude of 4 meters over ground degree;
The marginal separation price of the exhausts will not be a lot less than 10 metres/second; 1. Capacity of damage in weight: 60 Kg/h.
2. It has to have the capability to run not less than 10 hours/day
3. This burner needs to be able to spoil all flammable wastes produced by health care facilities, private facilities, research laboratories, institutes, and so on.
4. Style Demands: Types A, B, C, D, and also E of professional waste
5.” PYROLYTIC” burning, by controling the gasification of waste.
6. The heater needs to stay clear of the launch of black smoke along with wonderful dust, (Electric) throughout the loadings.
7. It has to be able to decrease the quantity of wastes by 98%.
8. It must have the ability to hold exhaust in the 2nd melt with gas home of not much less than 2 seconds.
9. The incineration ought to be entirely lacking recognizable smoke along with offensive smells.
10. – Article burning: >> 1100oC.
11. The Interior diameter of the Smokeshaft: Ø 400 and its elevation: 8 m.
12. The Quantity of the burning chamber: 1.200 L.
13. The Measurement of the door for filling in centimeters: 70×× × × 70.
14. Heater procedure have to be Automatic On/Off.
15. Gas: diesel.
16. The supplier needs to supply essential details for the greatest of the setup.
This burner with “PYROLYTIC” burning ought to have:
17. A burning chamber of waste:.
* Completely minimal door for the hand-operated loading of waste. The packing should be Guidebook, Batch Tons.
* A burner of lights which the usage is limited to the ignition of waste.
* Frontage of loading with door seals gone up on joints, wheel of screw plug, versatile joint, as well as packaging protecting out of refractory.
* The insulation of the combustion chamber need to be composed of refractory blocks, having a high internet content of aluminium and insulates blocks in order to ensure a minimum temperature level outside sheet steel.
* Structure of the refractory;.
– – Refractory concrete:
. Thickness: ≥ 100 mm.
– Nature: 42% of Al203.
– Shield in coarse panels:.
– Density: ≥ 75 mm.
– Nature: Calcium silicate. * Heating system of lights of waste, with gas, common mono-bloc spreading leading plunging fire, lights as well as additionally safety and security as well as security of electronic ignition, lasting air circulation, electromagnetic sluice entryway of regulation and additionally separating valve.
* Plate of burning in Carborundum, avoiding the repairing of glass and also slags.

18. A chamber of short article combustion of gases.
* A heater of burning of gases,.
* A tool of shot of air allowing a total recombustion of gases,.
* A gizmo of air inlet of cooling of waste gases,.
* A sheath of emptying of the gases charred.
* Carcass in strong sheet steel with help of link.
* Makeup of the refractory;.
– – Refractory concrete:.
Thickness: ≥ 150 mm
. – Shield in fibrous panel:
.
Nature: Calcium.
* Burner with gas, mono-bloc spreading leading kind with straight fire, illumination and also security and protection of electronic ignition, irreversible air flow, electro-magnetic sluice entrance of guideline and separating shutoff.
* A second shot of air to ensure best oxygen internet material.
19. A control box making sure the complete cycle of burning.

20. Fan:.
* Electro-ventilator dispersing the secondary air, the guideline of the air flow being performed by shutoffs as well as also adhering to the control of the automatic cycle.
21. Controls as well as guidelines:.
Control box watertight to dirt, including:

* A switch breaker for every single engine (ventilators in addition to burners).
* A timer with flexible temporization for the law of each burner.
* A regulatory authority with digital watching for the temperature of combustion.
* A regulatory authority with watch for the temperature degree of postcombustion.
* Electric box.

21. The de- ashing must be executed in lowest level of the burning chamber or the deashing should be Automatic or hands-on batch de ashing.
22. Fine-tune Filtering system: Scruber to be mentionned as optional.
23. Exhaust Needs Consistency: BS 3316 or équivalent requirement.
23. Ability to deal with Plastic: Very little less than 40% by weight.
24. CE Production Compliance: BS EN 746-2-1997.
22. The company ought to supply sets of extra components of extremely initial seriousness and also consumable of the burner.
23. The established burner must birth a one year guarantee.
24. The service provider will certainly perforn an onsite setup of the heater.
25. The technical training of operators will certainly have to be provided in addition to provided by an expert.
from the factory; it will include alleviative and preventative maintenance, as well as using device, etc


waste incinerator manufacturer in china

  1. Burning rate: 250 Kg/hr.
  2. It should be able to Operate not Less than 10 hours/day
  3. This incinerator must be able to destruct all combustible wastes produced by hospitals, private clinics, laboratories, institutes, etc…
  4. Design Specification: Types A, B, C, D, and E of medical waste
  5. “PYROLYTIC” combustion, by controlling the gasification of waste.
  6. The incinerator must avoid the release of black smoke and fine dust, (Smokeless) during the loadings.
  7. It should be able to reduce the volume of wastes by 98%.
  8. It should be able to hold emission in the second burn with gas residence of not less than 2 seconds.

The incineration should be completely free from visible smoke as well as offensive odours.

  1. The lower calorific power (L.C.P) of this waste will be 3,500 kcal/kg
  • The Temperatures of combustion:Minimum will be 850oC and max 1400oC
  • Post combustion: >1100o
  1. The Internal diameter of the Chimney: Ø 400mm² and its height: 8 Meter
  2. The Volume of the combustion chamber: Not Less Than 2.3 M³
  3. Burner operation should be Automatic On/Off
  4. Fuel : diesel, LPG, Natural Gas, Bio fuel
  5. The supplier must provide  necessary information for the best of  the installation

This incinerator with “PYROLYTIC” combustion must have:

  1. A combustion chamber of waste:

* Perfectly tight door for the manual loading of waste.The loading should be Manual, Batch Load,

* A burner of lighting which the use is limited to the ignition of waste.

* Top Loading loading with door seals gone up on hinges, wheel of screw plug, flexible joint, and stuffing insulating out of refractory.

* The insulation of the combustion chamber should be composed of refractory bricks, having a high content of aluminum and insulates bricks in order to assure a minimum temperature on   the outside sheet metal.

* Composition of the refractory;

  • Refractory concrete :
    • . Thickness : ≥100 mm
    • . Nature: 42% of Al203
  • Insulate in fibrous panels :
    • . Thickness: ≥75 mm
  • Nature: Calcium silicate.

* Burner of lighting of waste, with fuel, standard mono-bloc casting guiding plunging flame, lighting and safety of electronic ignition, permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.

* Plate of combustion in Carborundum, avoiding the fixing of glass and slags.

  1. Load Method: Top Loading

 

  1. A chamber of post combustion of gases

* A burner of combustion of gases,

* A device of injection of air allowing a total recombustion of gases,

* A device of air inlet of cooling of waste gases,

* A sheath of evacuation of the gases burnt.

* Carcass in strong sheet steel with support of connection.

* Composition of the refractory;

  • Refractory concrete :
    • Thickness : ≥180 mm
    • Nature: 65% of Al203
  • Insulate in fibrous panel :

производители мусоросжигательных заводов Китай

Способность Не намного меньше 500 кг / час.
Процедура Постоянная работа 24 часа-7 дней в неделю.
Камера сгорания 2 камера сгорания.
Температура. Камера сгорания 800-1000 С.
Секундное горение с горением 1000-1200 ° C, с возможностью повышения до 1400 ° C.
Эффективность сгорания 99,99%.
Время удержания циркулирующих газов не менее 2 сек в горячей части.
Избыточная концентрация кислорода в первичной камере сгорания 3-6% макс.
Огнеупор Камеры должны быть облицованы огнеупорными блоками с высокой теплоизоляцией с идеальной плотностью, а также с очень высокими температурами. сопротивление. Не менее 1400 ° C для первой камеры сгорания и не намного менее 1600 ° C для вторичной камеры сгорания, а также в то же время предотвращение температуры. наружного корпуса камеры не выше 70 С.
Двери должны быть облицованы таким же кирпичом, а стороны должны быть облицованы уникальным идеальным защитным материалом, чтобы избежать утечки любого вида газа, а также двери должны находиться в неблагоприятных условиях во время эксплуатации.
Система управления отводом воздуха Обладает высокой эффективностью устранения повреждений и устранения повреждений (DRE). Не менее 99,9999 по KEPA.
Влажная система Если система оборудована CEMS, промывающим циркулирующий газ водой, то она должна быть изготовлена из подходящих антикоррозионных материалов, а также оборудована pH-метром для измерения и уменьшения воздействия воды. Она должна иметь возможность использовать воду в закрытом оборотном контуре часто перед ее очисткой / сбросом прямо в канализацию в соответствии с KEPARS.
Химическое применение. Оно должно быть оборудовано соответствующей системой автохимического нанесения для регулирования pH воды в системе мокрого скруббера, состоящей из датчиков.
Дымоход Он должен соответствовать мощности, а также техническим требованиям, с высотой не менее 12 м от уровня земли. С простой открываемой точкой отбора проб, равной примерно 3 дюймам, и максимальные области отбора проб составляют как минимум 8D нижестоящих инструкций, а также 2D выше по течению от любых типов нарушений потока.
Фактор отбора проб. Необходимо оборудовать системой, расположенной ниже коэффициента отбора проб в диапазоне не намного меньше 1 м, а также оборудовать идеальной лестницей от земли до порта с удобным уклоном.
Удаление золы Это должна быть система удаления золы из автомобиля.
Топливо Это должна быть сдвоенная система, такая как дизель, а также газ.
Система подачи Должна быть автомобильной системой подачи в первичную камеру.
Зона управления должна быть оборудована панелью управления, показывающей Temp. подогревателей внутреннего сгорания, слежение за газом, цифровая температура. Индикация для первичной / вторичной камеры, электронная температура. знак для газов… и т. д. это также должно быть управление автомобилем, включение / выключение освещения автомобиля, автоматический запуск / остановка системы контроля выпуска воздуха, анализ системы непрерывного наблюдения за автомобильным газом, а также распечатка спецификаций выбросов газов… … И т. Д. Система кондиционирования воздуха Основная камера должна быть снабжена автоматической системой охлаждения через форсунки, чтобы обеспечить прямое кондиционирование воздуха при температуре. наверняка будет выше 1100 С.
Межблокировочная система Инсинератор должен быть оборудован межблокировочной системой для прекращения подачи отходов в первичную камеру при температуре горения. менее 500 С.
Терапия дымохода, а также очистка Состоит из единой системы (влажная / сухая), в которой используются вода, известь, энергетический уголь, а также керамические фильтры.
Система успокоения / Теплообменник Должен быть изготовлен, а также произведен из продуктов, устойчивых к коррозии и воздействию кислоты, таких как нержавеющая сталь 316 или аналогичные.
Уровень шума Не более 85 дБА при нормальной работе.
Кроме того, в проекте должно быть обеспечено использование гибких и безопасных систем управления.
Горелка должна быть установлена внутри закрытой соответствующей конструкции с хорошей вентиляцией, а также системой воздушного потока. В здании есть сооружения для выгрузки мусора из грузовых автомобилей. Автомобильная система мойки грузовиков, а также мусорных контейнеров, а также большие складские площади …… и т. Д.
. В предложение должен быть включен список оригинальных запчастей на 7 лет.
Предложение должно включать в себя надзор, запуск и обучение водителей, а также министерство здравоохранения и дизайнеров хорошего самочувствия в Кувейте и за его пределами.
Должны быть составлены углубленные рисунки, журналы.

medical waste incinerator manufacturer

GOODS:  ONE INCINERATORS IN ACCORDANCE WITH THE   SUPPLIER’    
REQUIREMENT   S OWN    
      PROPOSED    
         
      SPECIFICA    
      TION/      
      CONFIRM    
      ATION    
      SPECS    
  Incinerator walls and roof : 1550 °C castable monolithic refractory          
  concrete          
  Temperature: ≥90 °C          
  Insulation to walls: 1000 °C castable insulation          
  Electricity supply required: 220volt, 15amp single phase          
  Controls          
  Draught control: barometer indicator, door operated draught limiter          
  Air supply: built-in forced heated air ducts, primary and secondary          
  (intensifier)          
  Electric: control panel includes-circuit breakers, main switch, timer,          
  pilot lights, 2 set point pyrometer and one set point pyrometer          
             
  3.Experience and Qualifications          
  Experience and Qualifications          
  Company          
  The companies responding to this ToRs must have at least 5 year          
  experience of incinerator installation and maintenance or related          
  field. It must be registered, have trader’s licence and be compliant          
  with tax requirements.          
  Project Leader          
  The proposed expert should be able to demonstrate a breadth of          
  relevant experience in operations and maintenance of incinerators or          
  environmental management. The project leader should have at least          
  a degree in environmental management or mechanical engineering          
  or  related  field  with  at  least  5  year  experience  in  project          
  coordination.  Previous  work  in  Lesotho  or  Southern  African          
  Development Community (SADC) experience will be an advantage.          
  Health and Safety Officer          
  He/she  should  be  a  health  and  safety  professional,  such  as          
  occupational health and safety; safety, health and environment, with          
  at least 4 years of carrying out compliance inspections and audits of          
  incinerators or construction projects.  A minimum of a diploma in          
  health  and  safety  or  a  relevant  discipline  is  required.   Prior          
  experience in Lesotho will be an added advantage.          
37        

Residuos que pueden fundirse o quemarse

desperdicio en sí mismo, problemas de funcionamiento en la cámara del cobertizo (es decir, grado de temperatura, tiempo de mantenimiento y también perturbación) y también

capacidad del automovilista. Residuos que tienen materiales clorados (es decir, clorados

disolventes y plásticos, tuberías de PVC, madera tratada con pentaclorofenol o pintura modificada con PCB, madera flotante acuática)

deben dividirse de otros residuos diferentes, ya que su quema resultará absolutamente en el avance de novo, así como en el agotamiento de numerosos

dioxinas y furanos. Varios otros residuos que no deben perderse a menos que se utilicen especialmente creados

Los incineradores consisten en el uso de aceite lubricante, suelo contaminado con hidrocarburos, desechos biomédicos, lodos de alcantarillado o cualquier tipo de

otros residuos especialmente restringidos por el Departamento de Medio Ambiente.

solventes y plásticos, tuberías de PVC, madera tratada con pentaclorofenol o pintura modificada con PCB, madera flotante marina)

deben separarse de varios otros desechos, ya que su quema ciertamente resultará en el desarrollo de novo, así como en el escape de varios

compuestos de dioxinas y furanos. Residuos, incluido el mercurio (es decir, baterías, termostatos y bombillas fluorescentes), así como

varios otros metales pesados (es decir, baterías de plomo ácido, madera tratada con pintura con plomo) no deben quemarse como el mercurio

así como los aceros pesados no se arruinarán. Otros residuos que no se deben tirar a menos que se utilicen

Los incineradores consisten en aceite lubricante, suelo contaminado con hidrocarburos, residuos biomédicos, lodos de alcantarillado o cualquier tipo de

otros residuos específicamente prohibidos por la División de Medio Ambiente.

La Tabla 2 proporciona una lista de desechos típicos que se pueden eliminar y aquellos que requieren un factor especial a considerar y

terapia. Tenga en cuenta que la quema y la incineración al aire libre se reconocen como columnas separadas en la tabla que

Se aplican varias restricciones dependiendo del enfoque que se utilice. En general, muchas más restricciones se relacionan con la

diferentes técnicas de quema a cielo abierto debido a la combustión incompleta lograda. Menos restricciones impuestas

incineración como resultado de la capacidad del operador para controlar el procedimiento de combustión.

Los productos no combustibles, como el acero y el vidrio, no se queman tan bien y sin duda robarán el calor de los desechos que pueden ser

arruinado por la quema. Los residuos inflamables siempre deben separarse de los residuos no combustibles antes de ser llenados.

en la cámara de fusión.

INCINERATEUR BURNING DAMAGES OF MEDICAL WASTE PYROLYTIC Along With LABORATORY


Usage diesel, construction in repainted steel resistant aluminium at heats up, fire device control indication, billing indicator, temperature level control gadget, melting ability of 250 kg/ hr in 2 phases (2nd and primary electronic camera).
INCINERATEUR BURNING DEVASTATION OF MEDICAL WASTE PYROLYTIC AND ALSO LABORATORY.
1. CAPABILITY OF GARBAGE DISPOSAL: 50à60 kg/ h.
2. CAPACITY OF PROCEDURE WITHOUT PREVENTING: 10h.
3. SUITABLE FOR WASTE CATEGORIES A, B, C, D In Addition To E MEDICAL WASTE BY UNEP In Addition To THAT.
4. BURNING “PYROLYSIS” by regulating the waste gasification.
5. CALORIFIC LOWER (LCP) WASTE OF THESE NECESSITY BE OF 3500 KCAL/ H. a burner with filling up indication, temperature level control features and with 2 chambers (key as well as added).
6. TEMPERATURE LEVEL MAX 1400oC DESTRUCTION.
7. MINUTES TEMPERATURE LEVELS OF DESTRUCTION 850oC.
8. LOSING AREA NUMBER: 2 (PRIMARY Along With SECONDARY).
9. VOLUME CHAMBER: 1200L.
10. MEASUREMENT OF THE LOADING DOOR: 70CMX70CM.
11. GAS KIND: DIESEL.
12. POWER SUPPLY: 220 V/ 380 V.
13. SMOKESHAFT ELEVATION: 40 CENTIMETERS.
14. BURNER.
15. VANTILLATEUR BLOCK.
16. BOX CONTROL AND ALSO REGULATION.Diesel medical waste burner made from steel painted in light weight aluminum.
along with resistente to heats, device indication for fire.
control, packing indicator, temperature level control device, burning.
ability of 250Kg/ 10 hrs in 2 phases (key chamber and also.
added chamber.one should burn 50Kg/hr an added 600Kg/hr and an extra, 1000Kg/hr. I have actually visited your internet site as well as would love to ask the adhering to questions:.
1. Are these units sustained by gas?
2. Do the devices ship absolutely created or in products?
3. Are smoke stacks consisted of?
4. Can the systems be established within a city area or should they be outside city restrictions?
5. What flooring area does each system call for?
6. What sort of enclosure is required?
7. What is the normal gas consumption for every device?


incinerator manufacturers

GOODS:  ONE INCINERATORS IN ACCORDANCE WITH THE   SUPPLIER’    
REQUIREMENT     S OWN    
        PROPOSED    
           
        SPECIFICA    
        TION/      
        CONFIRM    
        ATION    
        SPECS    
  Height from base: 11m and if there are buildings within 30m of the          
  incinerator, chimney must extend at least 3m above the apexes of all          
  the roofs of such buildings            
  Diameter of chimney at top: 430mm          
  Weight of stack: ± 500kg            
  case and stack be painted with 400 °C heat resistant black paint          
  Burners            
  1st chamber 850 oC -900oC            
  2nd chamber 1000oC            
  Variable speed combustion air blowers          
  Primary chamber volume ±1.05 cubic metres          
  Mixing chamber volume ±0.30 cubic meters          
  Settling chamber volume ±0.89 cubic meters          
  Weight excluding chimney ±6 400kg at manufacture          
  Firing tools supplied: Hoe, poker and rake          
  Dimensions            
  Length ±2 125mm            
  Width ±1 890mm            
  Height  ±2 125mm            
  Extra width for burners ±1 000mm          
  Loading door opening 610mm×540mm          
  Hearth area ±1.19 square metres          
  Description of grate/hearth: A full hearth to be supplied to prevent          
  contaminated  liquids  from  flowing  into  ash  pit  without  being          
  incinerated            
  Compliance with South African Atmospheric Pollution Prevention          
  Act No. 45 of 1965 or equivalent air pollution standard          
  Documents to be supplied : Operations and maintenance manual and          
  standard operating procedures (SOPs)          
  Emission controls:            
  heated refractory screen            
  Low velocity grit settling chamber          
  Stainless steel arrester screen            
  Refractory material: alumina content ≥49% and thickness average          
  102mm            
  Bake out: to be done over 2-3 days          
  Materials of construction            
  Case: 5mm mild steel            
  Bracing: heavy angle and channel          
  Hearth: 1550 °C            
  Ashing door: high grade cast iron          
  Loading door 5mm mild steel lined with 1550 °C castable general          
  purpose high strength, high abrasion resistant monolithic refractory          
  concrete            
    36        

стоимость первичного сжигания клинической горелки

Наша обычная деятельность ежедневно создает 2-5 тонн различных отходов, которые варьируются от туш, а также цена основного сжигания в медицинских инсинераторах.

прочие отходы, которые необходимо сжигать при температуре дымовых выхлопных газов выше 800 градусов по Цельсию.

медицинские учреждения и учреждения для безопасного обращения с инфекционными и патологическими отходами.

Тонны Способность в диапазоне до 200 кг
– – Скорость горения прибл. 50 кг / час – –

Горелки должны быть действительно надежными, газоэффективными с высокими / пониженными скоростями плавления
и соответствовать нормам контроля загрязнения воздуха / DEFRA и т. д. Технологии:

Нагреватель с регулируемой температурой. Прочный корпус, чтобы быть качественным, прочным, надежным и доступным для клинических отходов.

Инсинератор с соответствующим контролем, очень простой в эксплуатации и самонесущий. Тип газа: дизельное топливо / нефть или нефть.
Системы должны быть предварительно собраны, предварительно смонтированы, смонтированы и оценены перед транспортировкой / экспортом.

В рамках назначения и совместной закупки экологического и медицинского оборудования и технологий это

Бюро закупок приветствует претендентов на предварительный квалификационный отбор с целью отбора квалифицированных фирм для участия в торгах.

для вышеуказанного тендера.
В поставку войдут уникальные устройства для надежного управления отходами, как указано выше для нового персонала.

Атмосферная компания по администрированию контрактов с подготовленными операциями в 2013 году в Индонезии, а также в Таиланде, а также в 2014 году на Западе и Востоке.

Малайзии предоставит эти экспертные услуги для выполнения требований федерального правительства по защите и утилизации.

для медицинских, больничных и профессиональных отходов в регионе, а также для выполнения более высоких технических стандартов в этом определенном

полевые. небольшие инсинераторы с фильтром (с наименьшим минимальным загрязнением) для сжигания / сжигания 5 кг / час, 10 кг / час, 15 кг / час,

20 кг / час, от 25 кг / час до 50 кг / час, а также 300 кг / час СИЛЬНОЙ ПРИРОДНОЙ СУХОЙ И ВЛАЖНОСТИ, НЕОПАСНОЙ любого вида (включая медицинские учреждения

отходов) ежедневно или в час. Должен ли он быть без дыма, без дыма, без запаха (запаха), без пыли, без выбросов твердых частиц

частицы и с наименьшим минимальным загрязнением (в рамках национальных, а также мировых критериев). Нужно быть эко

здоровые и сбалансированные, а также приемлемые по мировым критериям. Не нужно использовать скрубберы для воды. Зольные материалы после сжигания

должно быть 3-4%.

Incinérateur P déchets médicaux à Atmosphere contrôlé conçu pour À 'incinération des déchets biomédicaux



Incinérateur de déchets médicaux à air contrôlé conçu pour l’incinération des déchets biomédicaux générés dans un centre de traitement du sang. Les déchets à traiter comprennent principalement les biodéchets (c’est-à-dire les fluides corporels), les déchets infectieux et dangereux tels que les seringues, les aiguilles et autres déchets médicaux (c’est-à-dire les caoutchoucs de silicone, les plastiques, les textiles, les papiers, les emballages, etc.)

Spécifications opérationnelles Spécifications physiques
Volume de la chambre de combustion (m3) 8,80 m3
Taux de combustion * jusqu’à 1500 kg par heure
Consommation moyenne de carburant 65 kg par heure ou plus (7 brûleurs diesel)
Température opérationnelle 850 à 1320 ° C
Rétention de gaz dans la chambre secondaire Grande chambre secondaire
Surveillance de la température Oui
Résidus de cendres moyen (%) 3%
Dispositif thermostatique Oui
Réservoir de fumée diesel 1000l
Laveur de gaz Venture
Système d’alimentation hydraulique de bélier
Grand incinérateur à moteur diesel
Spécification minimale requise

Normes




TECHNICAL INCINERATORS SPECIFICATIONS FOR 2 hospitals in Kenya

TECHNICAL INCINERATORS SPECIFICATIONS FOR 2 hospitals

 

INTRODUCTION

  • All the incinerators to be supplied and installed must meet the Government of Kenya waste Management Regulation 2006 in particular 3rdschedule regulation (26, 47) pertaining classification, standards, criteria, and procedure for installing/operating incinerators as authored by the National Environmental Management and Coordination (waste management) regulation 2006, legal notice No. 121 of 29th September 2006
  • The capacity of the incinerator required should be to the specifications with a capacity to burn 100kgs/Hr
  • The incinerator shall be run on a 3-phase power supply (mains)
  • For the technical evaluation, not only the treatment plant but the entire system will be considered.  It will be the responsibility of the Bidder to supply a full system, including all eventually additionally necessary secondary systems and additional equipment.
  • The system offered shall be designed to operate normally under the conditions of the purchaser’s country. The conditions include Power Supply, Climate, Temperature, Humidity, etc.
  • The Bidder must provide a warranty for one year.
  • All text, parameter etc. on all control operating interfaces as well as on information displays and on print-outs shall be in English language.
  • The Bidder is responsible for all permits and approvals for importation. The Bidder shall provide all the necessary documentation in order to facilitate the legal requirements for the installation and putting into use of the equipment.
  • Period of Execution is 90 days from contract signature for delivery to site and completion of all verification operations required for the issuance of provisional acceptance.
  • Representatives of the Contracting Authority and the Beneficiary, together with the Bidder’s representative, shall carry out the controls, testing and initial approval for provisional and final acceptance as.  The provisional and final acceptance shall take place at the final destination.
  • After-Sales Service: The Bidder is required to ensure that a maintenance, service and repair centre, which is authorised by the Manufacturer, and which is able to rapidly supply genuine spare parts and consumables recommended by the Manufacturer is available throughout the one year warranty period. In fulfillment of this requirement with their offer Bidders must submit a statement signed by a representative of the manufacturer:
    • Providing the name and address of its authorised maintenance, service and repair centre,
    • Confirming that this authorised maintenance, service and repair centre is able to rapidly supply genuine spare parts and the consumables recommended by the Manufacturer; and

 

  • The Bidder will be responsible to deliver and install all to be supplied equipment at to be set up waste handling areas in the Republic of Kenya. The Bidder shall deliver a time schedule over the complete construction and assembling period. The delivery and installation time must be agreed between bidders, target Hospital and the Contracting Authority. The treatment plant must arrive pre-assembled. The Bidder shall ensure that all parts of the plant transported by sea shall not be shipped as “deck cargo”.

 

  • It is expected that the Bidder cooperates closely with the contractor for the new waste handling building/area and will make available all needed technical information, drawing, etc. to the contractor.

 

  • The Bidder shall supply and install the incinerator with the following attached specifications

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

           
TECHNICAL INCINERATORS SPECIFICATIONS FOR EAPHLNP
           
ITEM DESCRIPTION UNIT QTY RATE KSHS.
           
  Incinerator        
  To supply and install the following    2NO.    
  Hospital Incinerators to Nema standards        
  The following are the incinerator specifications :-        
A Ø      Waste type:      Mixed type 0,1,2,3 & 4 hospital/clinical bio hazard waste        
  Ø      Waste density:   125 to 350Kg/M³        
  Ø      Waste CV:        4000 KCAL/Kg        
  Ø      Moisture content:   10-25%        
  Ø      Estimated ash residue: 5-10%        
  Ø      Nominal capacity:   100Kg/hour batch load        
  Ø      Secondary chamber:  2 second @ 1100ºC        
  Ø      Environmental:    NEMA ACT           (EMCA) 1999        
                Clean Air Act 1999        
  BS3316 1987        
  Equipment Set      
  The Incinerator must comprise of: –        
  Ø      Manual Loading door (heavy duty steel door with appropriate refractory lining)        
  Ø      Horizontal solid hearth, refractory lined primary combustion chamber 800mm diameter x 2100mm long        
  Ø      Full sized bulk load/ash removal door        
  Ø      1 off diesel-fired ignition burner – temperature controlled        
  Ø      1 off combustion air supply fan and distribution system, automatic control        
  Ø      High capacity secondary combustion chamber 2 second @ 1100ºC with        
  Ø      1 off diesel-fired afterburner – temperature controlled        
  Ø      Control Panel – automatic operation        
  Ø      Temperature indication primary and secondary chambers 0-1200ºC. Both chambers must be insulated with refractory material (super duty 100mm thick firebrick with 25mm thick calcium silicate insulation)        
  Ø      Refractory lined flanged chimney to a height of 10M and it must be 3m above the height of any existing roof adjacent to the incinerator        
  Carried Forward To Collection Page.        
 

 

 

NOTE: WE REQUIRE TWO INCINERATORS. ONE        
ITEM DESCRIPTION UNIT QTY RATE KSHS.
B Diesel Tank:        
  To provide for diesel service tank (Capacity 400 litres) including level indicator

The tank should be connected to the incinerator at a higher level to enable free-flow of diesel from the tank to the incinerator. The connecting pipe must be a black pipe of approved gauge and diameter. Include other accompanying accessories and fittings

Item 1    
C Installation & commissioning works        
D Positioning of Incinerator: –

Provide lifting gears as forklift, gantry, rollers, and lifting jacks and position incinerator.

Item 1    
E Connect burners to fuel supply. No. 2    
F Chimney Installation:        
 G Composition of the chimney: –

Provide a chimney with scrubber (for filtration)

Provide lifting gear to hoist, erect and mount chimney, and provide supports slings as necessary. Allow for cutting of tree branches to facilitate the exercise.

The chimney shall be painted with approved heat resistant paint after installation.

Item. 1    
H Commissioning & Training:        
  Testing set operating parameters, training of operators and technical staff. Item 1    
I Commissioning Maintenance Contract        
  Before the expiry of the warranty/signing off, the suppler shall provide a one-year replacement service parts (e.g. filters, air filters), the Quarterly routine maintenance price per quarter for three (3) quarters. Maintenance contract proposal).  The maintenance contract price includes labour, transport and accommodation for the attending technicians. Item 3    

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

EVALUATION CRITERIA

Evaluation shall be carried out in four stages namely preliminary examination of documents for conformance with mandatory requirements, technical evaluation, site visit and commercial evaluation.

Stage One: Preliminary Examination

– Preliminary Evaluation under special condition of the tender. These are mandatory requirements.

This shall include confirmation that a bidder has complied with the special condition of tender above.

Failure to meet any one of the above requirements stated in the special conditions of the contract shall lead to automatic disqualification.

Stage Two: TECHNICAL EVALUATION (70 MARKS)

 

ITEM DESCRIPTION UNIT QTY MARKS ALLOCATED   MARKS RECEIVED  
           
  Incinerator        
  To supply and install the following    2NO.    
  Hospital Incinerator to Nema standards        
 

 

The following are the incinerator specifications :-        
           
A Ø      Waste type:      Mixed type 0,1,2,3 & 4 hospital/clinical bio hazard waste     35  
  Ø      Waste density:   125 to 350Kg/M³        
  Ø      Waste CV:        4000 KCAL/Kg        
  Ø      Moisture content:   10-25%        
  Ø      Estimated ash residue: 5-10%        
  Ø      Nominal capacity:   100Kg/hour batch load        
  Ø      Secondary chamber:  2 second @ 1100ºC        
  Ø      Environmental:    NEMA ACT           (EMCA) 1999        
                Clean Air Act 1999        
  BS3316 1987        
  Equipment Set      
  The Incinerator must comprise of: –        
  Ø      Manual Loading door (heavy duty steel door with appropriate refractory lining)        
  Ø      Horizontal solid hearth, refractory lined primary combustion chamber 800mm diameter x 2100mm long        
  Ø      Full sized bulk load/ash removal door        
  Ø      1 off diesel-fired ignition burner – temperature controlled        
  Ø      1 off combustion air supply fan and distribution system, automatic control        
  Ø      High capacity secondary combustion chamber 2 second @ 1100ºC with        
  Ø      1 off diesel-fired afterburner – temperature controlled        
  Ø      Control Panel – automatic operation        
  Ø      Temperature indication primary and secondary chambers 0-1200ºC. Both chambers must be insulated with refractory material (super duty 100mm thick firebrick with 25mm thick calcium silicate insulation)        
  Ø      Refractory lined flanged chimney to a height of 10M and it must be 3m above the height of any existing roof adjacent to the incinerator        
           
ITEM DESCRIPTION UNIT QTY RATE KSHS.
B Diesel Tank:        
  To provide for diesel service tank (Capacity 400 litres) including level indicator

The tank should be connected to the incinerator at a higher level to enable free-flow of diesel from the tank to the incinerator. The connecting pipe must be a black pipe of approved gauge and diameter. Include other accompanying accessories and fittings

Item 1 20  
C Installation & commissioning works        
D Positioning of Incinerator: –

Provide lifting gears as forklift, gantry, rollers, and lifting jacks and position incinerator.

Item 1 10  
E Connect burners to fuel supply. No. 2 5  
F Chimney Installation:        
 G Composition of the chimney: –

Provide a chimney with scrubber (for filtration)

Provide lifting gear to hoist, erect and mount chimney, and provide supports slings as necessary. Allow for cutting of tree branches to facilitate the exercise.

The chimney shall be painted with approved heat resistant paint after installation.

Item. 1 10  
H Commissioning & Training:        
  Testing set operating parameters, training of operators and technical staff. Item 1 10  
I Commissioning Maintenance Contract        
  Before the expiry of the warranty/signing off, the suppler shall provide a one-year replacement service parts (e.g. filters, air filters), the Quarterly routine maintenance price per quarter for three (3) quarters. Maintenance contract proposal).  The maintenance contract price includes labour, transport and accommodation for the attending technicians. Item 3 10  
  TOTAL      

100

 

 

Pass mark for technical evaluation is 70/100 marks

 

Stage Three: Site Visit

The evaluation committee will visit the premises of the bidders who are responsive to technical  evaluation stage to verify the authenticity of statutory document submitted; ascertain the accuracy of the information given in the tender documents, assess firm’s capacity, location, among others.

The Tenderer will be automatically disqualified where false or fraudulent Information is found to have been given.

 

Stage 4 Commercial Evaluation

Bids that pass the above three (3) stages shall be compared on the basis of prices / cost quoted and the lowest priced will be considered the lowest evaluated bid and subsequently recommended for award. Prevailing market prices will be used to determine the price responsiveness of the bidders.

 


SECTION V – SCHEDULE OF REQUIREMENTS

 

ITEM

NO

ITEM DESCRIPTION UNIT QTY. REQUIRED UNIT PRICE (KHS) REMARKS
1. Supply, Delivery, installation and commissioning of Incinerator in  

 

 

NO

 

 

 

 

 

 

1

   
2. Supply, Delivery, installation and commissioning of Incinerator  

 

 

NO

 

 

 

 

 

 

1

   

 

 

 

 

Signature of tenderer

 

Note: In case of discrepancy between unit price and total, the unit price shall prevail.

 

SECTION VI – STANDARD FORMS

 

  1. Form of tender
  2. Contract form
  3. Confidential Questionnaire form
  4. Tender security form
  5. Performance security form
  6. Bank guarantee for advance payment
  7. Declaration form