Archive: February 23, 2024

small capacity burners

1    Basic Plant Design    An approved plant must have four distinct sections that demonstrate three principles of Turbulence, Residence Time and Temperature are inbuilt in the plant design .The regulated sections may include but not limited to:

Overall plant layout.
Feed chamber/ charging
Primary Combustion Chamber.
Secondary Combustion Chamber.
Particulate Scrubbers
Acid Gas Scrubbers
The stack/ chimney.
2    Feeding And Charging    Controlled hygienic, mechanical or automatic feeding methods have to be used which will not influence the air temperature in the primary and secondary chambers of the incinerator negatively.

No waste is to be fed into the incinerator:

1.    Until the minimum temperatures have been reached.
2.    If the minimum combustion temperatures are not maintained.
3.    Whenever the previous charge has not been completely combusted in the case of batch feeding.

4.    Until such time as the addition of more waste will not cause the design parameters of the incinerator to be exceeded.

3    Primary Combustion Chamber    The primary combustion chamber must:

1.    Be accepted as the primary combustion zone.
2.    Be equipped with a burner/s burning gas/fuel or low sulphur liquid fuels. Other combustion methods will be judged on merits.

3.    Ensure primary air supply is controlled efficiently
4.    Ensure minimum exit temperature is not less than 850oC

4    Secondary Combustion Chamber (Afterburner).    The secondary combustion chamber must:

1.    Be accepted as secondary combustion zone.
2.    Be fitted with secondary burner/s burning gas or low sulphur liquid fuel or any suitable fuel.

3.    Ensure secondary air supply is controlled efficiently.
4.    Ensure flame contact with all gases is achieved.
5.    Ensure residence time is not less than two (2) seconds.
6.    Ensure the gas temperature as measured against the inside wall in the secondary chamber & not in the flame zone, is not less than 1100oC.

7.    Ensure the oxygen content of the emitted gases is not less than 11%.
8.    Ensure both primary and the combustion temperatures are maintained until all waste has been completely combusted

5    Particulate Removers    A mechanical particulate collector must be incorporated after secondary combustion chamber for removal of particulate pollutants entrained in the flue gas stream. The particulate collectors may include any of the following or a combination thereof:

Cyclone separator
Electrostatic precipitators
Fabric filters
6    Chimney / Stack    1.    The chimney should have a minimum height of 10 meters above ground level and clear the highest point of the building by not less than 3 meters for all roofs. The topography and height of adjacent buildings within 50 meters radius should be taken into account.

2.    If possible the chimney should be visible to the operator from the feeding area.
3.    The addition of dilution air after combustion in order to achieve the requirement of these guidelines is unacceptable.

4.    The minimum exit velocity should be 10 m/s and at least twice the surrounding wind speed (Efflux velocity = wind speed x 2) whichever is higher to ensure no down washing of exiting gases.

5.    Point for the measurement of emissions shall be provided.

7    Instrumentation    Instrument for determining the inside wall temperature and not burner flame temperature must be provided for both primary and secondary chambers.

2.    An audible and visible alarm must be installed to warn the operator when the secondary temperature drops to below the required temperature.

3.    In addition to the above the following instruments may also be required.
A carbon monoxide and/or oxygen meter/recorder
A smoke density meter/recorder
A gas flow meter/recorder
A solid particulate meter/recorder
Any other instrument or measurement that may be considered necessary

8    Location / Siting    1.    Must be sited in accordance with the relevant local municipal authority planning scheme, the topography of the area and be compatible with premises in the neighborhood,

2.    Must be housed in a suitably ventilated room.

9    Emission Limits    1.    Combustion efficiency:

Combustion efficiency (CE) shall be at least 99.00%
The Combustion efficiency is computed as follows;

C.E=             % CO2           x 100
% CO2 + CO

2.    The temperature of the primary chamber shall be 800 ± 50o C

3.    The secondary chamber  gas residence time shall be at least 1 (one) second at 1050 ± 50o C, with 3% Oxygen in the stack gas.

4    Opacity of the smoke must not exceed 20% Viewed from 50 meters with naked eyes
5.    All the emission to the air other than steam or water vapour must be odourless and free from mist, fume and droplets.

6.    The Authority may require that the certificate holder have tests carried out by an accredited institution to determine stack and/or ground level concentrations of the following substances.

Cadmium and compounds as     Cd
Mercury                                      Hg
Thallium                                     Tl

Chromium                                  Cr
Beryllium                                    Be
Arsenic                                       As
Antimony                                    Sb
Barium                                        Ba
Lead                                            Pb
Silver                                          Ag
Cobalt                                         Co
Copper                                        Cu
Manganese                                  Mn
Tin                                               Sn
Vanadium                                     V
Nickel                                           Ni
Hydrochloric                                HCL
Hydrofluoric acid                         HF
Sulphur dioxide                           S02

7.    A 99.99% destruction and removal efficiency (DRE) for each principal organic hazardous constituent (POHC) in the waste feed where:

DRE = [(Win – Wout)/Win]*100
Where: Win = mass feed rate of the POHC in the waste stream fed to incinerator, and
Wout = mass emission rate of POHC in the stack prior to the release to the atmosphere.

8.    The average dioxin and furan concentration in the emissions should not exceed 80ng/m3 total dioxins and furans if measured for a period of 6 to 16 hours.

Note:
All pollutant concentrations must be expressed at Oo C and 1.013 x 10 5 N/m2, dry gas and 11% oxygen correction.

Oxygen correction is computed as:

Es =     21 – Os    x EM
21 – OM

Where:    Es    = Calculated emission concentration at the standard percentage oxygen concentration
EM    = Measured emission concentration
Os    = Standard oxygen concentration
OM    = measured oxygen concentration

10    Operation    1.    Materials destined for incineration should be of known origin and composition and must be only incinerated in a furnace that is registered for the particular type of waste.

2.    A record must be kept of the quantity, type and origin of the waste to be incinerated.
3.    The incinerator must be preheated to working temperature before charging any waste.
4.    The incinerator must not be overcharged.
5.    The incinerator must be in good working order at all times and must not be used if any component fails. Any malfunction should be recorded in a log book and reported to the relevant authority.

6.    The incinerator operator and all relevant staff must be trained to the satisfaction of the relevant control authority.

11    Housekeeping    The site where the incinerator is built must:

1.    Have running water.
2.    Have a solid floor.
3.     Have lighting if 24hrs operation
4.    Have fly ash containerization and storage before disposal.

12    Health & Safety (Protective Gear)    1.    Staff handling waste must be well trained on safe handling of hazardous wastes
2.     Staff must be provided with appropriate  protective gear such as, gas mask, aprons, gumboots, helmets, gloves, goggles.

3.     Caution and Warning signs must be provided.
4.     Fire fighting equipment must be provided
5.     There should be no smoking or eating on the site.

waste incinerator producers china

Ability Not much less than 500Kg/hr.
Procedure 24hr-7days/ week constant operation.
Burning chamber 2 burning chamber.
Temperature. Burning chamber 800-1000 C.
Secandry combustion burning 1000-1200 C, with the possibility to be upgraded to 1400 C.
Combustion Efficiency Effectiveness 99.99%.
Retention time Of the circulation gases not less than 2 Sec in the hot part.
Excess Oxygen concentration Of primary burning chamber 3-6% max.
Refractory The chambers must be lined with high thermal shielding refractory blocks with ideal density and also with extremely temperature. resistance. Not less than 1400 C for the first combustion chamber, and not much less than 1600 C for the secandry combustion chamber, and also at the exact same time prevent the Temp. of the outside body of the chamber not higher than 70 C.
Doors Must be lined with the very same bricks, and the sides lined with unique ideal shielding product to avoid any kind of gas running away, and also the doors must be kept under unfavorable stress during the operation.
Air Exhaust Control System With high damage and elimination performance (DRE). Not less than 99.9999 based on KEPA.
Wet System If the system equiped with a CEMS washing the circulation gas with water, then it must be produced from suitable anti corrossion materials, and also equiped with pH meter to gauge as well as reduce the effects of the water. It ought to be able to utilize the water in shut recycled circuit often times prior to treating/ discharging right into the sewage system in compliance with KEPARS.
Chemical application It must be equiped with appropriate autochemical application system to manage the pH for the water of the wet scrubber system consisting of sensing units.
Chimney It need to be suitable with the capacity as well as the technical requirements, with height not much less than 12m from ground degree. With simple opennable sampling point equal about 3 inch, and the maximum sampling areas is at the very least 8D downstream instructions and also 2D upstream from any type of flow disturbancies.
Sampling factor Needs to be equiped with a system situated down the sampling factor by a range not much less than 1 m, and also equiped with ideal stairs from ground to the port with comfortable slope.
Ash Removal It need to be vehicle ash removal system.
Fuel It ought to be twin system, such as diesel as well as gas.
Feeding System Should be car feeding system into primary chamber.
Control Area Should be equiped with a control board shows Temp. of the combustion heaters, gas tracking, digital Temperature. indecation for the primary/secondary chambers, electronic Temperature. sign for the gases … etc. it ought to be also Car operation, burnures on/off car lights switch over, auto start/stop for air discharge control system, automobile gas continual surveillance system analysis as well as print out of gas emission specifications…… etc. Air conditioning System The main chamber ought to be given with auto cooling systemthrough nozzles to permit direct air conditioning if the Temperature. will certainly be heigher than 1100 C.
Inter-lock system The incinerator should be equiped with inter-lock system to stop feeding the waste to the primary chamber if the burning Temperature. less than 500 C.
Flue therapy and also cleansing To consist a consolidated system (wet/dry), making use of water, lime, energetic carbon as well as ceramic filters.
Appeasing system/Heat exchanger Must be made as well as produced from anti rust and acid attack products such as stainless steel 316 or comparable.
Noise Degree Not greater than 85 dBA throughout normal operation.
Inaddition The desigh ought to insure that responsive secure control systems are utilized.
The burner should be mounted inside closed appropriate structure with great oygenation as well as air flow system. The building has facilities for off-loading of wastes from transport lorries. Automobile cleansing system for trucks and also waste containers, and also great storage area…… and so on
. The quotation ought to included list of original spare components for 7 years.
The quotation must consist of supervising, launching and training of the drivers and also ministry of health and wellness designers inside/outside Kuwait.
In-depth drawings, magazines ought to be consisted of.

Unidad de calentamiento de incineración para quemar patalogical

sistema de calefacción de incineración para derramar patalogical (como células humanas o sangre) como el oeste

El peso de estos productos west es de 700 kg mensuales y de igual forma requerimos un calentador aislado.

Sin humos además de cualquier tipo de gas dañino

. REQUISITOS DEL INCINERADOR

# Resumen de especificaciones

1 Capacidad de combustión – – – – 400 kg / hora y tampoco debe ser mucho menos de 300 kg / hora. El tiempo máximo de combustión debe ser de 6 veces al día.

2 Diámetro exterior del conducto de humos – – – – 300 a 400 mm

3 Potencia del ventilador – – – No debe superar los 1,1 kw

4 Voltaje – – – – 220V

5 Ingesta de aceite – – – No debe superar los 14 kg / h

6 Medida diagonal de la puerta de alimentación (mm) – – – – No mucho menos de 500 mm 7 Temperatura de incineración. (⁰ C) – – – – 800 o más 8 Escape

Monóxido de carbono – – – – No debe exceder los 100 mg / m3

SO2 – – No debe exceder los 400 mg / m3

HF – – – – (fluoruro de hidrógeno) No debe exceder los 9,0 mg / m3

NO2 – – – – No debe superar los 500 mg / m3

Suciedad de humo – – – – No es necesario superar los 100 mg / m3

9 Elevación del quemador – – – – Muy poco menos de 10 m sobre el nivel del suelo

10 Garantía de la solución del fabricante – – – – No mucho menos de 1 año

11 Enlace eléctrico – – – – Desde la caja de circulación sanguínea más cercana utilizando un cable eléctrico de 25 mm2 y además todos los enlaces y circuitos pertinentes

animal incinerator cost

 

 

The incinerator shall be able to incinerate both liquid and solid as per data below;

 

 

Liquid waste to be incinerated

 

The sludge to be incinerated is composed exclusively of a water and oil mixture in any proportion from the diesel power

plant running on heavy fuel oil. A sample specs of the heavy fuel oil used is annexed for info.

For capacity requirement, the characteristic of the sludge is as follows; Composition:

Water: 20 %,

Sludge derived from Heavy Fuel oil : 75 % Sludge derived from waste lube oil : 5 %

Mixed: Homogeneous with the diameter of solid particles not exceeding 0.8 mm

Temperature of sludge: 70 deg celcius Calorific value : around 8000 Kcal / Kg

Incinerators room for 3 incinerators as item 3-1-1, and waste store for keeping wastes for 7 days, including all

constructions by reinforced concrete with Incenerator and store equipment, all wiring, lighting, water supply and

drainage

 

 

Flow rate of sludge to be incinerated: 200 – 275 l/h Burning capacity: 1800 – 2400 KW

Provide Incinerators room & waste store with fire fighting system, including sprinklers, approval of water source at

site, fire alarm system contains sensors for heat & smoke, to be linked with the hospital fire alarm systems

Сжигатель КЛИНИЧЕСКИХ БИОЛОГИЧЕСКИХ ОТХОДОВ

Горелка должна быть трехкамерной.
Грузоподъемность 250 кг.
Реальность для мусоросжигательного завода должна быть способной выдерживать высокие температуры и, кроме того, различные другие полезные требования.
Дымовая шахта обязательно должна иметь прочную огнеупорную ячеистую футеровку из особого бетона, выдерживающую температуру выше 1200 ° С.
У него должно быть прочное основание, чтобы устройство оставалось надежным, прочным, а также безопасным и надежным, а также безопасным на протяжении всего срока службы.
Первичная (обжиговая), а также вторая (обжиговая) камеры должны быть оборудованы горелками для надежного горения.
В третьей камере скрубберы вместе с электрофильтрами обязательно нужно будет установить в качестве оборудования для контроля загрязнения перед выбросом газов прямо в окружающую среду.
Система постоянного мониторинга выхлопных газов, а также экологического отслеживания.
Система для обработки дренажа перед сбросом прямо в канализацию.
Необходимо использовать устройства контроля температуры, а также устройства наблюдения (термостат зондов), чтобы гарантировать достижение идеальных уровней температуры в камерах на протяжении всей обработки.
Электродвигатель (толкатели), достаточный для подачи достаточного количества воздуха прямо в камеры сгорания, а также для отвода газов к дымовому валу 9).
Электроэнергия большой мощности, а также звено генератора аварийных ситуаций для целей автоматического розжига.
Дымоход должен быть достаточно высоким, а также как минимум на один метр выше самой большой конструкции вокруг.
Бензобак (коммерческое дизельное топливо) должен быть разработан рядом с горелкой, но для выполнения функций безопасности, а также для защиты от возгорания. Способность 250.
Различные различные другие потребности
Обучение всех сотрудников, задействованных в обращении с отходами здравоохранения (МО).
Система автоматической подачи нагревателя
Система автоматической загрузки отходов с конвейерной лентой. Они направят отходы в начальную главную камеру.
Автоматическая система выгрузки золы.

clinical burner primary combustion cost

Our normal activities creates 2-5 tons of various waste products daily which vary from condemned carcasses, and also medical incinerator main combustion price

other wastes all which need to be blazed at above 800Centigrade gauged flue exhaust gas.To be used by small

healthcare facilities and facilities to safely take care of infectious as well as pathological wastes.

Tons Ability in the range of as much as 200 kg
– – Burning Rate approx. 50kg/Hour – –

Burners to be really reliable, gas efficient with high/ reduced ability melt rates
and to be made to meet the Norms of Air Pollution Control/ DEFRA, etc. Technology:

Temperature Controlled Heater. Heavy-duty housing, to be a quality, rugged, trustworthy, affordable Clinical Waste

Incinerator with relevant control, very easy to run and also self-supporting. Type of Gas: Diesel/ Oil or Petroleum.
Systems to be pre-assembled, pre-piped, pre-wired & & evaluated before Transport/ Export.

Within the structure of an environmental and medical equipment & & technology appointment and joint buying, this

Procurement Bureau welcomes applicants for pre-qualification in the purpose of mainly picking qualified firms to bid

for the above tender.
The supply will make up the unique devices for reliable waste administration as stated over for a new personal

atmosphere contract administration company with prepared operations 2013 in Indonesia as well as Thailand, as well as 2014 in West & & East

Malaysia to accomplish those expert services in order to abide by the federal governments safety and security disposal needs

for medical as well as hospital, professional waste in the region and also to fulfill the greater technical standard in this certain

field.small incinerators with filter (with the very least minimum pollution) for burning/combusting 5kg/hr, 10kg/hr, 15 kg/hr,

20kg/hr, 25kg/hr to 50kg/hr and also 300kg/hr of STRONG NATURAL DRY AND DAMP NON-HAZARDUOUS of any kind (including healthcare facility

wastes) daily or per hr. Should it be with no smoke, no fumes, no odour (odor), no dust, no emission of solid

particles and with the very least minimal contamination (within national as well as worldwide criteria). Need to be eco

healthy and balanced as well as acceptable with worldwide criteria. Need to not be with water scrubbers. Ash materials after burning

should be 3-4%.

производители мусоросжигательных заводов Китай

5-1- Камера дожигания установлена в фойе сгорания, elle est constituée d’un

Cylindre métallique revêtu intérieicing d’une couche d ‘изолятор et d’une couche de matériaux réfractaires.

5-2- Внутренний объем: 2,1 м3

Предусмотренное измерение для обеспечения температуры дымообразования от 2 секунд до 1100 ° C с сохранением температуры свободного кислорода.

d’au moins 6%.

5-3 -Аксессуары

? Trappe de visite boulonnée frontal pour permettre l’inspection périodique

? La liaison à la chambre de горения есть tapissée de réfractaire

? Установка файлов?

? Установка des sondes de mesure température

  1. PRODUCTION DE L’AIR COMBURANT DE LA CHAMBRE DE ПОСЛЕ СГОРАНИЯ

? Вентиляторная центрифуга

? Tuyauteries de distribution d’air

? Série de vannes de distribution d’air

? Soupape de régulation de l’air soufflé asservi par la sonde du debit d ‘Oxygène

  1. BRULEUR DE LA CHAMBRE DE ПОСТ СГОРАНИЯ

Sont prévus 2 br? Leurs du type à l’air soufflé au gasoil équipés des dispositifs de sécurité.

A la mise in route du four les deux br? Leurs sont allumés для обеспечения минимальной температуры воды при температуре 1100 ° C;

ils restent en marche successivement pour maintenir la température constante.

Puissance thermique installée (290 + 350) кВт.

  1. ХИМИЧЕСКАЯ ЭВАКУАЦИЯ

Вертикальный металлический трубопровод длиной 8 м с установкой в шкафу для ПК, диаметр 630 мм

en t? le d’acier au carbone avec garnissage intérieur en réfractaire

  1. ARMOIRE ELECTRIQUE DE COMMANDE ET REGULATION

Composée de ?:

Цепь 380 В- 50 Гц-3 фазы

? Voyant су напряженность

? Commande d’arrêt général

? Voyant état des bruleurs

? Affichage des températures des deux chambres

«Minuterie des temps des циклы».

? Неоднородные вариации жизнедеятельности вентиляторов

Таблица и кабели без дополнительных настроек CEI со степенью защиты IP 55

? Микропроцессор для контроля и регулирования температуры, ainsi que les циклы операций

? Cablages réalisés selon les règles CEI.

  1. ИНСТРУМЕНТ УПРАВЛЕНИЯ И ИЗМЕРЕНИЯ ПРОДОЛЖЕНИЕ

Les dispositifs suivants sont prévus ?:

1) Термопары для измерения температуры в камере сгорания? et postcombustion, à la sortie de

l’échangeur dans la section d’entrée du filter

2) Система измерения концентрации оксигена в дымовых газах с увлажнением в камере сгорания после сжигания.

constitué de ?:

? Зонд для измерения оксигена на оксиде циркония

? Помпе а ля мембрана

? дебитметр

Инсинератор должен быть поставлен Подрядчиком на условиях аренды в месте, установленном Компанией. В

Подрядчик должен предоставить обученный и компетентный персонал для первоначальной установки, ввода в эксплуатацию и эксплуатации.

обучение под наблюдением специалиста производителя. Инсинератор должен обслуживаться и эксплуатироваться в

спецификациям производителя обученным персоналом. Подрядчик должен иметь достаточный персонал, обученный и компетентный, чтобы

эксплуатировать мусоросжигательный завод в течение всего срока действия контракта. Технические характеристики инсинератора приведены в Приложении А.

hospital incinerator style

INCINERATEUR DE DECHETS HOSPITALIER hospital incinerator layout

SPECIFICATIONS TECHNIQUES.
Capacité damaging de 55 Kg/h jour de déchets hospitaliers avec un p?. c. i jusqu’ à 3.200 Kcal/Kg
1) Kind de déchet

hospitalier
2) Pouvoir calorifique inférieur 3.200 kcal/kg
3) Humidité 20%.
4) Teneur en cendres et/ou inertes 8%.
5) Capacité destructive nominale 55 kg/h.
6) Quantity chambre de burning 1,65 m3.
7) Quantity chambre postcombustion 2.1 m3.
8) Temps transportation des fumées en post burning/ sec. << 2. 9) Température minimale en postcombustion 1.100 ° C. 10) Teneur d'oxygène libre en postcombustion 6%. 11) Acknowledgment refuse confectionné en sachets HDPE. 12) Dispositif de chargement?: hydraulique?; capacité de charge 0.5 m3

13) Flammable prévu Gasoil.
14) Br?leur en chambre de combustion nbr?: 1.
15) Br?leur en chambre de postcombustion nbr?: 2

CONSTITTUTION DE L’APPAREIL.
1. CHARGEMENT.
Système de chargement hydraulique afin de pouvoir battery charger le 4 en toute sécurité même durant child fonctionnement et

aussi assurer la puissance devastating globale de 450 kg/j?
Le système comprend?:.
1-1Trémie de chargement de forme parallélépipédique de 0,5 m3 de volume, réalisée en t?le d’acier, bridés sur la paroi

frontale de la chambre de burning et munie d’un couvercle à charnières actionné par vérin hydraulique?.
Dimensions?:.
oLongueur 1200 mm.
oHauteur 700 mm.
oLargeur 600.
1-2Un poussoir hydraulique assurera le chargement de la chambre de combustion.
1-3 Une porte de chargement de la chambre de combustion constituée d’une guillotine à vérin hydraulique revêtue

de réfractaire.
1-4Un main hydraulique put piloter tous les vérins de commande, comprenant?: réservoir, pompe, électrovannes et

tuyauteries

2. CHAMBRE DE COMBUSTION PRIMAIRE

2-1- Le bati est une structure métallique cylindrique revêtue intérieurement d’une couche d’isolant et d’une

couche de réfractaire.
2-2-Volume intérieur?: 1,65 m3.
2-3-Aménagement.
? portillon de décharge des cendres?: frontal?; monté sur double charnière et revêtu de réfractaire avec hublot

d’inspection.
? La connexion à la chambre de chargement est revêtue de réfractaire.
? La connexion de la chambre de combustion et de la chambre de article combustion est revêtue de réfractaire.
? Setup des bruleurs.
? Setup du système de circulation de l’air comburant.
? Installment des sondes de mesure de la température.
? Le bac de récolte des cendres est en acier au carbone sur roulettes, équipé de racloir métallique permettant

l’évacuation manuelle des cendres.
3. BRULEUR DE LA CHAMBRE DE COMBUSQTION.
Un bruleur de kind à une flamme à l’air soufflé, alimenté the same level gasoil, équipé des dispositifs de sécurité Puissance

thermique installée 165 KW.
4. AIR COMBURANT.
Le système de distribution et dosage de l’air primaire en chambre de burning comprend?:.
? Ventilateur centrifuge.
? Canalisations de distribution air.
? Systéme de circulation d’air à 2 canaux.
? Soupape de régulation de l’air motorisé selon les phases de cycle de fonctionnement et de la température

5. CHAMBRE DE POST BURNING.
5-1- Chambre de article burning est installée au dessus du foyer de combustion, elle est constituée d’un

cylindre métallique revêtu intérieurement d’une couche d’ isolant et d’une couche de matériaux réfractaires.
5-2- Volume intérieur?: 2,1 m3.
Est dimensionnée put pouvoir garantir un temperatures de fumée de 2 secondes à 1100 ° C avec un pourcentage d’oxygène libre

d’au moins 6 %.
5-3 -Accessoires.
? Trappe de visite boulonnée frontal put permettre l’inspection périodique.
? La intermediary à la chambre de burning est tapissée de réfractaire.
? Setup les br?leurs.
? Installation des sondes de mesure température.
6. MANUFACTURING DE L’AIR COMBURANT DE LA CHAMBRE DE POST COMBUSTION.
? Ventilateur centrifuge.
? Tuyauteries de distribution d’air.
? Série de vannes de circulation d’air.
? Soupape de régulation de l’air soufflé asservi par la sonde du débit d’ oxygène

7. BRULEUR DE LA CHAMBRE DE MESSAGE COMBUSTION.
Sont prévus 2 br?leurs du type à l’air soufflé au gasoil équipés des dispositifs de sécurité.
A la mise en route du four les deux br?leurs sont allumés pour assurer la température minimale d’au moins 1100 ° C?;

ils restent en marche successivement pour maintenir la température constante.
Puissance thermique installée (290 + 350) KW.

8. CHEMINEE D’EVACUATION.
Constitué the same level un avenue métallique vertical de 8 m de long installée au-dessus de la chambre de COMPUTER, diamètre 630 mm

en t?le d’acier au carbone avec garnissage intérieur en réfractaire

9. ARMOIRE ELECTRIQUE DE COMMANDE ET GUIDELINE.
Composée de?:.
? Circuit 380 V- 50 HZ-3 stages.
? Voyant sous stress.
? Commande d’arrêt général.
? Voyant état des bruleurs.
? Affichage des températures des deux chambres.
? Minuterie des temps des cycles.
? Une variation des vitesses des ventilateurs.
? Le tableau et les cablages sont prévus aux règles CEI avec security IP 55.
? Microprocesseur put le contr?le et la régulation des températures, ainsi que les cycles d’opération.
? Cablages réalisés selon les règles CEI.

10. INSTRUMENTATION DE CONTROLE ET DE MESURAGE CONTINU.
Les dispositifs suivants sont prévus?:.
1) Thermocouples pour la mesure de la température en chambre de combustion? et postcombustion, à la sortie de

l’échangeur dans la area d’entrée du filtre.
2) Système de mesure de la concentration d’oxygène dans les fumées humides a la sortie de la chambre de postcombustion

constitué de?:.
? Sonde de mesure de l’oxygène à l’oxyde de zirconium.
? Pompe à la membrane.
? débitmètre

un quemador de animales para la cremación de mascotas

Tenemos un centro clínico de 70 camas en Namibia. Existe la posibilidad de obtener clientes de muchos otros médicos regionales.
¿Puede proporcionarme alguna información sobre este tipo de incineradores (pequeño conjunto)? Será absolutamente un uso solitario de cada mascota por separado. Inicialmente nos estamos preparando para comenzar este Trabajo Piloto con el Centro Médico Nacional, para persuadir a los Funcionarios del Ministerio y sobre su éxito para llevar esta tarea a los Hospitales Docentes, Ubicación y también Base Hospitales del Municipio del País demandan 4 crematorios para cadáveres. Necesito información sobre el precio, el tipo de energía para la activación, los gases de escape peligrosos. El incinerador que estamos buscando debe tener las ventajas del sistema de reciclaje Cozy, el uso de agua caliente, etc.