burner manufacturers



1. SCOPE OF FEATURE The work specified in the agreement will certainly consist of.
1. Supply, place as well as assign a heater as given in the technological specifications
2. Specification for adherence to OSHA along with other legal demand associating with Health and wellness of staff members throughout execution of the works covered in this tender.
3. Analysis and also prep work as well as building and building of a standard burner shed with one waste storage room (see the design)

4. Stipulation of treatment and also maintenance guidebooks as well as illustrations complete with upkeep schedule and guidelines.

5. Gas oil storage tank- Light steel1500 litres ability

6. Onsite training for operation in addition to maintenance team.

CRUCIAL
Tenderers that fail to conform with this need totally will have their tenders refuted. TECHNOLOGICAL NEEDS OF THE REQUIRED BURNER

2.1 General Recap

The plant have to have 4 unique areas that show 3 principles of turbulence, home time and likewise temperature level retention.
1. Overall plant layout
2. Feed chamber/charging
3. Key burning chamber
4. Particle scrubbers
5. Acid gas scrubbers.
6. The stack/chimney.
7. Minimum capability of crucial chamber = 0.18 cubic metres
8. Dropped price (price of waste incineration) = a the very least 20 kg per human resources
9. Need to have a full dimension counterbalance filling door enabling very simple access to the main chamber for filling as well as getting rid of ash.
Supply, Setup and also Appointing of A Burner in Eastern Hydros [Web Page 28

2.2 Feeding and additionally Billing
Controlled sanitary mechanical feeding that does not negatively influence the air temperature degree in the trick as well as likewise 2nd chambers of the heater shall be made use of.
2.3 Key Burning Chamber.

a) This chamber need to be outfitted with burners that make use of low sulphur gas.
b) The chamber should ensure a marginal leave temperature degree of 850 levels centigrade.

2.4 Secondary Burning Chamber (After burner)

a) Should be fitted with heating systems that utilize low sulphur gas.
b) Assurance 2nd air supply is controlled.
c) See to it residence time is not much less than two secs.
d) Guarantee that the gas temperature level as gauged versus the within wall in the extra chamber and also not in the fire location is not much less than 1100 levels centigrade.
e) Make sure the discharged oxygen web material of the sent out gases is not much less than 11%.
f) Assurance both primary as well as second burning temperature level levels are preserved up till all waste is totally ignited.

2.5 Particulate Removers

A mechanical fragment lover need to be incorporated after 2nd burning chamber for removal of particle toxic substances entrained in the flue gas stream. The particle collection agencies may include any of the abiding by or a mix thereof:.
a) Cyclone separator.
b) Electrostatic precipitators.
c) Fabric filters.
2.6 Chimney/Stack

l) The smokeshaft need to have a marginal altitude of 10 metres above ground degree in addition to clear the acme of the framework by not much less than 3 metres for all roofs. The topography along with elevation of nearby structures within 50 metres span must be thought about.
m) The smokeshaft should certainly show up to the motorist from the feeding area.
n) The minimal leave price require to be 10 metres per second in addition to at least twice the bordering wind speed (Efflux speed = wind speed x 2) whichever is higher to make sure no down cleaning of leaving gases.
o) The point for measurement of discharges will certainly be offered.

2.7 Instrumentation

a) Tool for finding out the within wall temperature as well as likewise not heater fire temperature level must be addressed both also second as well as key chambers.
b) A additionally noticeable and distinctive alarm system requirement to be mounted to signal the operator when the second chamber temperature degree drops to listed here the called for temperature.
c) A carbon monoxide gas as well as additionally oxygen meter/recorder should be provided

d) A smoke density meter/recorder require to be supplied.
e) A strong particulate meter/recorder should certainly be provided.
f) Any sort of various other tool that may be taken into account essential.

2.9 Exhaust Province

a) Burning efficiency (C.E) shall go to the very the very least 99.00% where C.E = %Co2 x 100/ [% CARBON DIOXIDE + carbon monoxide] b) The temperature degree of the main chamber will certainly be 800 +/- 50 degrees centigrade. c) The additional chamber gas house time shall most likely to the very least 1 second at 1050 +/- 50 levels centigrade with 3% oxygen in the pile gas.
d) Opacity of the smoke demand to not exceed 20% seen from 50 metres with naked eyes.
e) All the discharge to the air besides vapor or water vapour must be odor free and without mist, fume and also grains.
f) A 99.99% devastation and removal efficiency (DRE) for every single primary all-natural hazardous element (POHC) in the waste feed where DRE [( Success – – – – Wout)/ Win] x 100 where Success = mass feed price of the POHC in the waste stream fed to burner as well as Wout = mass exhaust price of POHC in the pile prior to the launch to the atmosphere.
g) The typical dioxin and likewise furan concentration in the exhaust should not exceed 80mg/m3 overall dioxins and furans if gauged for a duration of 6 to 16 hrs.

– – – – Guidebook technological monitoring is delivered with the devices with all descriptions of failings in addition to resolutions.
Capacity/island: 4000 kg/day; 25000 kg/day; 31000 kg/day; 48000 kg/day

Burning temperature– – over 12000C

Two chambers– – minimal

Wears down– – dioxin as well as additionally significant metaly– – much better after that Kyoto procedure

Discharge– – tracking system

Waste unloiding– – straight from waste track to incinerator



pet crematory

The temperature is over the minimum and under the maximum required temperature (e.g 1150?C) of the thermal

reactor (partial load).

 

When switching off, only the solenoid valve for the fuel supply closes, the burner fan stays on to cool and protect the

burner head.

 

The reactor burner shall be modulating burner with pre-ventilation working on the principle of an oil pressure atomizer

with return nozzle for diesel oil, consisting of:

 

–      Fan housing with high-powered fan and cover

 

–      Electric motor

 

–      Oil pressure pump with built-in oil pressure controller

 

–      Burner nozzle rod with return nozzle and baffle plate

 

–      Coupled control with servomotor, rate controller, regulating segment and air valves

 

–          Electromagnetic shut-off dampers

–      Burner tube with flame pot, burner connection and insulation flange

 

–      Electrical high voltage ignition with ignition transformer and ignition electrodes

 

In the control panel:

 

–      Oil firing sequence control automation relay.

capacity – 50 Kg

 

Burn rate – 20 Kg/h

 

maximum Temperature – 1000C

 

Operating Energy – Diesel

 

Ignition method –

 

Combustion chambers – 2

 

Insulation – refractory Lining

 

No of burners – 2

 

Loading Method – Front load with safety latch

 

Chimney – Heavy duty stainless steel

 

Control – Burner control

 

Thermostat control

 

Timer control

 

Fan timer control

 

Instrumentation -4 Digit temperature display

 

Ash removal – Separate ash removal door

 

Fuel consumption per Kg –

 

Automatic & simple to operate control pannel –

 

3 mm steel casing & fully insulation

 

Dense  refractory concrete lining rated to 1400 degree to C

 

safety chute for easy loading –

 

SS Flue as standard –

 

Heat recovery option –

 

Easy onsite Installation –

manufacturer of ha zardous waste incinerator in china

Burning Capacity: 125 kg minimum/time (3-6times/day), double chamber, double combustion system
Imputing door Mouth Width (mm): 760*760 (approx.)
Chimney External Diameter (mm): 300 ± 10
Combustion Improver Device: 0.11kw, Fuel consumption: 7kg/ hour (max)
Re-Burning Device: Oil consumption: 5kg/h, 0.37kw, Oil consumption: 10-20kg/h
Voltage: 380v/220v AC, Warranty: 1 Year, 50 Hz

Per your advertisement for 300 kg.hr. Model – We need to know the price via return.

How many Kg. of Fuel would be required for running this Model 10 hrs. everyday.

We have our own Freight Forwarding Agent.

We had a Contract for Garbage Management before their Civil War for 120 Tons/Day for one Municipality in North Africa
Medical Waste Incinerator

Dual Chamber (Primary & Secondary) with insulation slabs (fully insulated internal refractory lining) along with

controlled air blower for each chamber

Insulation / Refractory Thickness: ≥ 100mm

Chamber plate thickness: ≥ 6mm

Fuel Type: Natural gas based on burning fuel in combustion chambers

Waste Capacity: ≈ 150 Kg/Day

Incineration capacity: ≈ 25 Kg/Day (Separate waste charging and waste removal doors)

Burners: At least with (02) burners of automated start and stop functions

Combustion efficiency: > 97%

Temperature: programmable temperature with temp monitoring system

Residence time: 2 second in secondary chamber

Heating value: 4000 Kcal

Temperature Range: ≈ min 800ºC to max 1200ºC

Electrical supply: 220V with single phase

Chimney Plate Thickness: ≥ 5mm

Water scrubber: Scrubbing using reagent like lime & should made of SS 10 gauge of non-corrosion properties and painted

exteriorly by equipment grade heat resistive enamel

Chimney Height: between 15-25 feet

small incinarator

heavy Duty Steel casing

 

High Quality refectory lining & insulation

 

1 x Diesel fired ignition burners operated on / off

 

Front Loading Door (safety catch

 

Separate Ash removal Door

 

 

2.7  CONTROL UNIT

 

  1. The entire processing cycle and the combined effect of the individual components of the incinerator shall be

achieved by a central control unit.

 

  1. The control panel shall consist of a standardized sprayed sheet steel shell with doors and the necessary

mounting supports and contains all the devices such as relays, time switch, safety device, contactors, regulator,

display devices, recorder, selection, on, off and main switches, and indicator lamps required for the control,

regulating and registration.

small home incinerators

Equipment Access Openings: Arrange all equipment and piping to allow access to openings without disassembly of

equipment or piping. Provide space which permits full opening of all doors, panels, and other access openings.

 

  1. Operating Space: Do not reduce or alter personnel working spaces shown except with prior approval of Resident

Engineer.

 

  1. Fuel Oil System: Coordinate set pressure of house fuel oil system with requirements of burner mounted pumps. Do

not exceed inlet pressure limitations (typically 14 kPa or 2 psi or less), or suction lift capabilities of burner

mounted pumps.

1.Capacity of destruction in weight: 60 Kg/h.

2.It should be able to operate not less than 10 hours/day

3.This incinerator must be able to destruct all combustible wastes produced by hospitals, private clinics,

laboratories, institutes, etc…

4.Design Specification : Types A, B, C, D, and E of medical waste

5.“PYROLYTIC” combustion, by controlling the gasification of waste.

6.The incinerator must avoid the release of black smoke and fine dust, during the loadings.

7.It should be able to reduce the volume of wastes by 98%.

8.It should be able to hold emission in the second burn with gas residence of not less than 2 seconds.

9.The incineration should be completely free from visible smoke as well as offensive odours.

10.The lower calorific power (L.C.P) of this waste will be 3,500 kcal/kg

The Temperatures of combustion: Minimum will be 850oC and max 1400oC

Post combustion: >1100oC.

11.The Internal diameter of the Chimney: Ø 400 and its height: 8 m

12.The Volume of the combustion chamber: 1.200 L

13.The Dimension of the door for loading in cm: 70×70.

14.Burner operation should be Automatic On/Off

15.Fuel : diesel

16.The supplier must provide  necessary information for the best of  the installation

This incinerator with “PYROLYTIC” combustion must have:

17.A combustion chamber of waste:

* Perfectly tight door for the manual loading of waste. The loading should be Manual, Batch Load

* A burner of lighting which the use is limited to the ignition of waste.

* Frontage of loading with door seals gone up on hinges, wheel of screw plug, flexible joint, and stuffing insulating

out of refractory.

* The insulation of the combustion chamber should be composed of refractory bricks, having a

high content of aluminium and insulates bricks in order to assure a minimum temperature on

the outside sheet metal.

* Composition of the refractory;

 

Refractory concrete :

. Thickness      : ≥100 mm

. Nature: 42% of Al203

Insulate in fibrous panels :

. Thickness: ≥75 mm

Nature: Calcium silicate.

* Burner of lighting of waste, with fuel, standard mono-bloc casting guiding  plunging flame, lighting and safety of

electronic ignition, permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.

* Plate of combustion in Carborundum, avoiding the fixing of glass and slags.

diesel oil fired medical waste incenerator

High Temperature Waste Incinerator Model D. MB 750XL Burn Rate-150Kg/hour minimum Weight(Kg)-4000kg Secondary Chamber

(double chamber with post-burning) Gas Retention Time 2 second Fuel Diesel Power Supply for control box 220V-240, single

phase 50-60Hz Minimum operating temperature 1200 oC One year spare parts package for complete maintainability 10m hose

pipe. 1100 litre fuel Tank +pipe system Containerised (the container will serve as housing) Additional chimney extension

1 metre high One (1) year warranty.

Incinerator of 20 Kg : 03 Units

Electrically controlled incinerator.

Two-compartment incinerator with a capacity of 20 kg / hour.

Incinerator with low maintenance and operating costs; Equipped with an automatic control panel and easy to use with

electromagnetic locking of the door.

A main waste reduction chamber of 900 ° C. A post secondary combustion chamber of gases generated in the primary chamber

at least 1100 ° C.

Carbon residues in ash less than 5% by weight in accordance with European Directive 2000/76 / EC.

With refractory lining in materials of higher quality
1/ Cost of a 200kgs/Hr medical waste incinerator.
2/ (CIF Term) Cost of shipping from factory to PAPUA NEW GUINEA seaport of LAE, Morobe province
3/ Cost of 2 Clover engineers to Supervise, Installation, Training our engineers and commissioning the medical; waste

incinerator.

pet animal cremation equipment

A chamber of post combustion of gases

* A burner of combustion of gases,

* A device of injection of air allowing a total recombustion of gases,

* A device of air inlet of cooling of waste gases,

* A sheath of evacuation of the gases burnt.

* Carcass in strong sheet steel with support of connection.

* Composition of the refractory;

Refractory concrete :

Thickness : ≥150 mm

Nature: 65% of Al203

Insulate in fibrous panel :

Thickness: ≥85 mm

 Nature: Calcium

* Burner with fuel, mono-bloc casting guiding type with horizontal flame, lighting and safety of electronic ignition,

permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.

* A secondary injection of air to ensure perfect oxygen content.

19.A control box ensuring the complete cycle of combustion.

 

20.Fan:

* Electro-ventilator distributing the secondary air, the regulation of the air flow being carried out by valves and

following the control of the automatic cycle.

21.Controls and regulations:

Control box watertight to dust, including:

 

* A switch circuit breaker for each engine (ventilators and burners).

* A timer with adjustable temporization for the regulation of each burner.

* A regulator with digital watching for the temperature of combustion.

* A regulator with digital watching for the temperature of postcombustion.

* Electric box.

 

  1. The de- ashing must be done in the bottom of the combustion chamber or the deashing should be Automatic or manual

batch de ashing.

  1. Process Filtering system : Scruber to be mentionned as optional
  2. Emission Standards Compliance: BS 3316 or équivalent standard
  3. Capacity to treat Plastic: Not less than 40% by weight
  4. CE Manufacturing Compliance: BS EN 746-2-1997

22.The supplier must give batches of spare parts of first urgency and consumable of the incinerator.

23.The installed incinerator must bear a one year guarantee.

24.The supplier shall perforn an onsite installation of the incinerator.

  1. The technical training of operators will have to be provided and given by a technician from

the factory; it will consist of curative and preventive maintenance, and the use of machine, etc

msw incinerator manufacturers

standard type, 11m long ,self supporting

Capacity-220kgs/hr

refuse-hospital waste

average moisture-15-20% on fist time

DIMENSIONS

height: 2710mm

length: 2840mm

Width; 2450mm

loading door opening: 610mm x 610mm

Grate/Heath Area: 2.0(square meters)

Primary chamber volume: 2.4(cubid  meters)

secondary chamber volume :2,72(cubid meters0

total volume: 5,12(cubid meters)

minimum stack diameter :560mm

 

  1. 300 kg per day healthcare waste incinerator

 

 

 

Our preferred technology is double-chamber incineration, but if you recommend an alternative technology, that is

acceptable as well.

 

 

 

We request information on the following for each of the above requirements:

 

 

 

  1. Capital cost (delivered cost in Oman)

 

 

 

  1. Operation and maintenance costs (per year)

 

 

 

  1. Number of operators required

 

 

 

  1. Product specifications (sizes, temperatures, residence time, cycle time etc)

 

 

 

  1. Other auxiliary equipment that is required or recommended by you

 

 

 

  1. Any other information and inputs that can facilitate the project and add value

 

 

  1. Would this mean that the plant would operate only 12 hours per day? Normally operating the station 24 hours

per day should be able to valorize 12 tons per day for an installation with a capacity of 500 kgs/hr.

Hiclover bio waste incineration



HICLOVER now offer a full range of containerized incineration systems, placing us at the forefront of the latest transportation and industrial trends. Containerization enables immediate waste management as the units are pre-assembled and pre-installed.
Containerization is the most feasible and viable option in contrast to the construction of on-site facilities and housing structures, eliminating the man power and costs involved. The system has the added benefit of total mobility (both local and international), and is ideal for military and civil camps and remote locations where infrastructure is scarce.

※ Main Quality:— — — — — Dual Burning Chamber — — Dual Italy Burner – – Burning Cost: 10-100kgs per hr–– – – Burning Chamber: 0.1M3-1.2 M3— — — — Mobile Incinerator, Requirement delivery containers, Easy to move/transport system— — — — Free Installment, Pre-installed heater, Suitable for camps— — — — Ultraviolet light sanitation inside

Items/Model TS10(PLC) TS20(PLC) TS30(PLC) TS50(PLC) TS100(PLC)
Burn Rate (Average) 10 kg/hour 20 kg/hour 30 kg/hour 50 kg/hour 100 kg/hour
Feed Capacity(Average) 20kg 40kg 60kg 100kg 200 kg
Control Mode PLC PLC PLC PLC PLC
Combustion Chamber 100L 210L 330L 560L 1200L
Internal Dimensions 50x50x40cm 65x65x50cm 75x75x60cm 100x80x70cm 120x100x100cm
Secondary Chamber 50L 110L 180L 280L 600L
Smoke Filter Chamber Yes Yes Yes Yes Yes
Feed Mode Manual Manual Manual Manual Manual
Voltage 220V 220V 220V 220V 220V
Power 0.5Kw 0.5Kw 0.5Kw 0.7Kw 0.7Kw
Oil Consumption (kg/hour) 5.4–12.6 7.8–16.3 10.2–20 12.1–24 14–28
Gas Consumption (m3/hour) 6.2–11.4 8–15.7 9.8–20 9.9–26.1 10–32.2
Temperature Monitor Yes Yes Yes Yes Yes
Temperature Protection Yes Yes Yes Yes Yes
Oil Tank 100L 100L 100L 100L 200L
Feed Door 30x30cm 45x40cm 55x50cm 70x55cm 80x60cm
Chimney 3Meter 3Meter 5Meter 5Meter 10Meter
Chimney Type Stainless Steel Stainless Steel Stainless Steel Stainless Steel Stainless Steel
1st. Chamber Temperature 800–1000 800–1000 800–1000 800–1000 800–1000
2nd. Chamber Temperature 1000-1200 1000-1200 1000-1200 1000-1200 1000-1200
Residency Time 2.0 Sec. 2.0 Sec. 2.0 Sec. 2.0 Sec. 2.0 Sec.
Gross Weight 1500kg 2200kg 3000kg 4500kg 6000kg
External Dimensions 140x90x120cm 160x110x130cm 175x120x140cm 230x130x155cm 260x150x180cm
Equipment Double chamber medical infectious waste incinerator Capacity 10-30 kg per hour Characteristics of waste
Mainly syringes and needles from immunization routine and campaign activities. However, the following average characteristics are considered*:
heating value above 2000 kcal/kg (8370 kJ/kg); content of combustible matter above 60%; content of non combustible solids below 5%; content of 
non-combustible fines below 20%; moisture content below 30% by weight
Combustion performance: The medica waste incinerator shall be capable of reducing waste to ash not exceeding 10% of the total combustible 
charges.
Outdoor installation. The medical waste incinerator will be installed outdoors. All incinerator components shall be suitable for but not 
limited to outdoor shaded installation, including electric motors, be resistent to corrosion, moisture and related weather elements.

Products of building and building and construction: The burner will certainly not have any type of asbestos, asbestos-containing products, mercury thermostats, as well as mercury switches. Refractory products will have the ability to meet appropriate standards under ISO TC33 and likewise CEN/TC 187.

Kinds of incinerator style appropriate: Dual-chamber controlled air incinerator or double- chamber pyrolytic burner


WWW.HICLOVER.COM|Waste Incinerators |Auto Roll Air Filters

Nanjing Clover Medical Modern Technology Co., Ltd.

Tel: +86 -25 -8461 0201 Site: www.hiclover.com Email: [e-mail       secured] Email: [e-mail       secured]



medcial incinerator manufacturer

The successful Bidder shall inform CEB in writing at least three (3) weeks prior to the carrying out of factory tests

so as to enable sending of one CEB Engineer for witnessing  of  the  factory  tests.    A  ‘Factory  Acceptance  Test

’  schedule  shall  be

 

mutually agreed between the successful Bidder and the CEB Engineer.

NOTE: All charges inclusive of air tickets, food & hotel accommodation, local transportation and other living expenses

for the CEB Engineer shall be borne by the successful Bidder.

The successful Bidder shall submit to the CEB Engineer the following documents prior to shipment of the incinerator

set.

 

 

?     Certificate of Conformity inclusive of the clause ‘We certify that, subject to exceptions or concessions

listed here after, the supplies detailed above were manufactured in accordance with the technical specifications of the

contract, order and that, all inspections and tests having been completed, the supplies comply in every aspect with the

relevant particular specifications, drawings, and relevant standards and regulations in force’.

?     Factory Acceptance Test(FAT) Certificates

?     Bill of Material (BOM)

?     Three(3) Complete Sets of As-Built Drawings

?     Installation and commissioning procedure for the incinerator set.

?     Program of works for carrying the installation and commissioning

?     Labour  and  logistic  requirement  for  carrying  the  installation  and commissioning.

?     All electrical drawings and wiring diagrams

Type of Waste: To treat medical waste, categories A, B, C, D,E

Type of incinerator: Pyrolytic

Nominal Burn Rate: 50 to 60 Kg/hrat  3500Kcal/Kg

Loading: Manual, Batch Load

De ashing: Automatic or manual batch de ashing

The incinerator must avoid the release of black smoke and

fine dust, during the loadings

Primary Chamber Capacity: 2 -3 m3

The insulation of the combustion chamber should be composed of

refractory bricks, having a high content of aluminium and insulates,

The plate of combustion in carborundum avoiding the fixing of

glass and slags

Hours of operation/day: >10 hrs

Max operating Temperature : 14000C

Normal Operating Temperature (Primary): >8500C

Operating Temperature (Secondary): >11000C

It should have temperature regulators in digital watch:

Carbon Content of Ash: <2%

The installation should be completely free from visible smoke as well

as offensive odours.

Residence Time in Second Chamber: 2 seconds minimum

The Internal diameter of the Chimney : Ø 400

Height of Stack:  >8 m

Burner operation: Automatic On/Off

Fuel: Diesel

Fuel Consumption at rated capacity: >7 Kg waste/ltr

Electricity Consumption: <2kW at rated capacity

Operating Voltage: 220-240VAC 50 Hz

Spare Parts: Supply for 1 year quoted as option

Consumables: Supply for one year of operation to be mentioned

as option

Warranty: Parts and service support: 1 year minimum post

commissioning

Service Support: <72 hours.

Emission Standards Compliance: BS 3316 or équivalent standard

Process Filtering system: Scruber to be mentionned as option

CE Manufacturing Compliance: BS EN 746-2-1997

Design Specification: Types A, B, C, D, and E of medical waste

Installation and Commissioning: Included in conditions of supply

Training in preventive and curative maintainance and use

of the incinerator: Operator training inclusive in offer

Capacity to treat Plastic: Not less than 40% by weight

Shed of the incinerator

Shelter of the incinerator inclusive in offer (the shelter must have

facilities for hand washing and firefighting).

This material and equipment must include in the shed of the

incinerator:

*   Foundation in rubble stone,

*   Isolation roofing against humidity;

* Elevation with brick of 20 cm (bloc cement), continuing lintel

(linteau) in reinforced concrete;

*  Steel frame (charpente en metal);

* Roofing in sheet B.C.A. 28 BG (Toiture en tôle),metal gutter,

*  Sanitary installation (wash basin, soak way pit of 20 m of depth);

*  Ash pit of 30 m3,

* Electrical installation;

* Concreteslab for fixing the incinerator;

* Chanel for evacuation of rain water or waste water

*  Wiremesh for aeration up the lintel;

* smoothrougtcasting of walls (interior and outside);

* plinth with cement;

*  2 metal doors ;

*  Enemail paintings inside and latex paintings outside the shelter

on walls and on doors;

*  Roofing limit (planche de rive);

*  Measures for this specification will depend on the size of the

incinerator which will determine the size of the shed of the incinerator.